Guide · Storage tanks
How to estimate the cost of a shop-built storage tank
Two tanks of the same volume can differ in price by a factor of two. A 10 m³ stainless dairy tank on legs with a dished bottom, an agitator and a jacket is a very different job from a 10 m³ flat-bottomed carbon steel water tank. This guide walks through how a small atmospheric tank is priced, and what really moves the number.
1. Start from a datasheet
You cannot price a tank from its volume alone. Fix these first:
- Service, product density and design temperature
- Material: carbon steel, 304L or 316L, and the surface finish (hygienic polish costs real hours)
- Orientation and size: diameter, shell height, vertical or horizontal
- Top and bottom: flat, sloped, cone, dished, ellipsoidal, dome or open
- Supports: legs, skirt, flat bottom on a foundation, or saddles
- Nozzle schedule, manways, instruments, ladders, insulation and cladding
- Corrosion allowance and the design standard
2. Size the plates
For a small tank the shell thickness is rarely set by the hoop stress. More often it is the standard's minimum thickness for the diameter, the next stock plate, or a local check at a nozzle or support. The usual one-foot method gives the design thickness of each course:
td = 4.9 D (H − 0.3) G / (Sd E) + CA
with D in metres, H the liquid height above the bottom of the course in metres, G the specific gravity, Sd the allowable stress in MPa and E the joint efficiency. Check the hydrotest case too, then adopt the next stock plate above the largest requirement. Formed and cone bottoms are checked at the pressure of their lowest point; a cone-to-shell junction may need a compression ring.
Once the thicknesses are fixed, the plate take-off follows from the geometry and the stock plate sizes, with an allowance for nesting and offcuts.
3. Nozzles, supports and lifting
Openings larger than about NPS 2 need their removed area replaced by spare shell thickness, the neck and, if needed, a pad. Legs are sized for the full weight plus wind overturning, with a slenderness check on the free length. Skirts, base rings and anchors are checked for the same moment, saddles for shear and horn stresses. Lifting lugs carry the empty weight with a dynamic factor and a sling angle.
Each of these adds parts, welds and hours, which is why a tank with twelve nozzles on legs costs much more than a plain one of the same weight.
4. Build the man-hours from the work
Count the work rather than applying a rate per tonne:
- Plate cutting and edge preparation, by length
- Rolling the shell courses (in-house or by a subcontractor)
- Forming heads and cones, usually bought in or subcontracted
- Fit-up and welding of seams, by weld length and thickness
- Nozzles, pads, manways, legs, lugs and attachments, per item
- Pickling and passivation or polishing for stainless; blasting and painting for carbon steel
- Hydrotest, NDT (spot radiography on seams that carry liquid head, penetrant on stainless attachment welds), inspection and documentation
Material factors matter: stainless steel takes longer to cut, weld and finish than carbon steel.
5. Vendor items and exclusions
Agitators, instruments, spray balls and special valves are vendor items. Price their nozzles, pads and installation, but list the items themselves for the vendor's quotation. Also state what is outside the price: transport, foundations, erection, seismic design, GST and anything subcontracted without a quote.
6. From cost to price
direct cost = material + labour (engineering, shop and NDT hours × their rates)
price = direct cost × (1 + contingency) × (1 + markup)
Keep contingency and markup separate. Contingency covers what is not yet known about this tank; markup is your business decision.
What usually drives the cost
- Material: stainless plate costs several times carbon steel, and hygienic finishes add hours.
- Formed bottoms and tops: dished and cone heads are expensive to make or buy.
- Number of nozzles and attachments: each one is cutting, fitting, welding and testing.
- Supports: legs with rings and pads, or a skirt, add significant fabrication.
- Process extras: agitator mounts and cooling jackets.
Price a tank in minutes. The Atmospheric Storage Tanks tool takes one datasheet and returns the design check (API 650 or AS 1692), drawings, material take-off, man-hours and an indicative price. See a full sample report, read the user manual or watch the tutorial.