Guide · Pipelines
How to split a pipe line into shop spools
A pipe line is rarely fabricated in one piece. It is cut into spools that are made in the shop, shipped and joined on site. Where you put the breaks decides how much work is done in the shop, where it is cheap and controlled, and how much on site, where it is slow and expensive.
Why the split matters for the estimate
Every break adds a field joint. A field weld on site can take several times the hours of the same weld in the shop: access, scaffolding, weather, fit-up in position and NDT in the field. Too few breaks, though, and the spools will not fit on a truck or through the plant. A good split keeps as much work as possible in the shop while every spool can still be lifted, shipped and installed.
Where to break the line
- At the transport limit. A spool should fit a standard truck without a permit, roughly 12 m long, 2.4 m wide and 2.6 m high. Check all three dimensions: a spool with a vertical leg can be short and still too high.
- At valves and inline items. Flanged valves, strainers and instruments are bolted in on site. The line naturally breaks at their flanges.
- Where installation needs it. Breaks near pipe racks, wall penetrations and equipment nozzles let the site team adjust and align the line.
- For handling and lifting. Long, flexible or heavy spools may need extra breaks or lifting points.
Field weld or flange pair?
A break can be a field weld (bevelled ends, joined on site) or a pair of weld-neck flanges (bolted on site).
- Field weld: cheaper material, but site welding, NDT and often a field hydrotest. Better for long buried or rack lines where flanges add leak points.
- Flange pair: two flanges, a gasket and a bolt set more, plus two shop welds; site work is only bolting. Better where the line must be removed for maintenance, or where site welding is restricted.
Estimate each spool as its own shop order
Once the line is split, each spool has its own cut list, weld register, NDT selection, hydrotest and drawing. Estimate each one on its own, then add the line items:
- Field joints: welds or bolted flange pairs between spools
- Valves and inline items between spools
- Site bolting materials: gaskets, studs and nuts
- Project management and QA/QC for the line as a whole
- Engineering for the line: spool drawings, weld maps, test packs
Shop work and site work should be shown separately, so the client can see the effect of moving a break.
A quick checklist
- Every spool inside 12 × 2.4 × 2.6 m?
- Breaks at every flanged valve and inline item?
- Field welds where site welding is allowed, flange pairs where it is not?
- Each spool with its own drawing, weld numbers and test?
- Field joints and site bolting listed in the line summary?
Let the tool split it. The Pipeline Spool Fabrication tool takes the whole line card by card, splits it at your Break and Valve cards and wherever a spool would not fit the truck envelope, and estimates every spool with its own report, isometric, weld record and cut list. One package for the whole line, from A$99.