Preview. Drawing sheet 1 and the report cover are shown; the other sheets and pages are in the final report (see the sample). The final report (PDF report and drawings, Excel, Word and the material take-off) carries its own report number and check code.
List the spool from the start face to the finish face. Pipe length is centre line: from the start face, an elbow centre or a branch centre to the next one. Turns are relative to the pipe before them. Fittings are ASME B16.9 butt weld; NPS 1-1/2 and smaller are ASME B16.11 socket weld Class 3000. Olets are MSS SP-97, swage nipples MSS SP-95 (size changes at NPS 1-1/2 and smaller always use one). A pipe nipple can replace the branch pipe in a branch card.
NPS ½ to 24 in carbon steel (A106 B, A53 B), low-temperature carbon steel (A333 Gr 6) and stainless steel (304L, 316L), with schedules to ASME B36.10 / B36.19 and flanges to ASME B16.5, class 150 to 1500. Fittings are ASME B16.9 butt weld; NPS 1½ and smaller are ASME B16.11 socket weld, Class 3000.
No. The design is by others: you enter the spool as it is drawn, and the tool prices and draws its fabrication. There are no wall-thickness or stress calculations. NDT, test pressure and heat treatment follow the client specification; the tool suggests defaults.
Activity by activity: handling per metre, one cut per piece, one bevel per butt-welded end, butt welds per joint by size and wall, flange attachment, branch and socket welds, preheat and PWHT when used, blasting and painting by area, QC, hydrotest per end, NDT per weld examined and engineering per weld. Stainless steel carries its own factors. Every line can be overridden, and the report marks your changes.
Cut length = centre-line length − the take-out of the fitting or flange at each end − half the root gap at each bevelled end. Pipe to buy is the sum of the cut lengths plus a 5% cutting loss. A piece shorter than 50 mm gives a warning.
RT, UT, MT (carbon steels) and PT, as a percentage of the shop welds in each group. The tool picks the welds, largest and thickest first, and lists them in the weld register; you can tick the welds yourself instead. Category M adds a sensitive leak test.
Price, man-hours and duration, the material take-off (also as Excel and CSV for purchasing), the cut list, the weld register with NDT, and four A4 drawings: general arrangement, 3D view with item and weld numbers, spool isometric with BOM, and the weld and test record. A$99 per spool, GST included; the first report is 80% off.