USER MANUAL

Estineer
Pipe Spool Fabrication

Shop-fabricated pipe spools, NPS ½ to 24: material take-off, cut lengths, welds, man-hours, price, drawings and reports
Pipe Spool Fabrication
www.estineer.com / support@estineer.com
Edition 1, November 2026. Engine version 1.50.
Software output only: must be checked and approved by a qualified engineer. Not engineering advice and not an estimate or quotation.
ESTINEERPipe Spool Fabrication, User Manual / Contents

CONTENTSManual outline

1Introduction and quick start
What the tool is, what it covers, the screen, one spool in five steps
2Inputs, field by field
Every field and component card: meaning, unit, default, limits
3How the estimate is calculated
Cut lengths, welds, weights, man-hours, cost, schedule, with figures
4Outputs
Tabs, drawings, PDF report, Excel, Word, MTO, ids and verification
5Worked example
SP-101 cooling-water spool, every number shown
6Limits and questions
What is not covered, messages, frequent questions, glossary
Pipeline Spool Fabrication. The companion tool that splits a whole line into shop spools uses the same engine, inputs and outputs. It has its own short manual covering only what it adds: break and valve cards, the line package and the line summary.
www.estineer.com2
ESTINEERPipe Spool Fabrication, User Manual / Chapter 1 Introduction and quick start

CHAPTER 1Introduction

1.1 What the tool is

The Estineer Pipe Spool Fabrication tool prices the shop fabrication of one pipe spool and produces its fabrication drawings. You copy the spool from the client's isometric: the material, size, schedule and flange class, then each component in fabrication order, from the start face to the finish face. The tool builds the spool in 3D, cuts the pipe into pieces, lists every weld, takes the weights and prices from its catalogue, builds the man-hours activity by activity and turns them into a cost, a price and a schedule.

The design is by others. The tool does not size the pipe or check it for pressure, stress or support: the line class and the isometric come from the client's piping design. It does check what matters to the workshop: pieces too short to weld, the transport envelope, the shop test pressure against the flange class, heat treatment and the NDT scope.

1.2 What goes in and what comes out

YOU ENTER Tag, line, service, projectMaterial, size, schedule, classComponents in fabrication orderEnd types and branchesFinish, NDT, hydrotestSubcontract quotesRates, contingency, markupFrom the client's isometric ESTINEER ENGINE 3D route and fittingsCut lengths and weld listWeights from the catalogueMaterial take-off (MTO)Activities and man-hoursCost, contingency, markupSchedule and drawingsCatalogue database + rules YOU GET Live 3D model and sketchCost, price, man-hours, weeksCut list and weld registerFour A4 drawingsEstimate report with exclusionsPDF, Excel, Word, MTOIds and check codeAll from one model
Figure 1.1 What goes in, what happens, what comes out. There is no AI in the number path: every figure comes from the engine and the catalogue database.

The same model drives the 3D view, the drawings, the report and the Excel and Word files. Change a field and all of them change together. Enter the same inputs twice and you get the same result; every purchased report carries a check code that proves which inputs, engine version and database produced it.

1.3 Conventions

www.estineer.com3
ESTINEERPipe Spool Fabrication, User Manual / Chapter 1 Introduction and quick start

1.4 What the tool covers

ItemCovered
SpoolOne shop-fabricated spool: straight runs, elbows, reducers, tees, half couplings, olets, end flanges
SizeNPS ½ to 24 for the run; branches and olets down to NPS ½
ConstructionButt-welded ASME B16.9 fittings above NPS 1½; socket-weld ASME B16.11 Class 3000 at NPS 1½ and smaller
MaterialsCarbon steel (A106 B seamless or A53 B ERW), low-temperature carbon steel (A333 Gr 6), stainless 304L and 316L
FlangesASME B16.5 weld neck, slip-on, socket weld and blind, Class 150 to 1500
RouteUp to 12 straight runs of 20 mm to 12 m each, and up to 6 branches
Finish and testBlast and paint systems for carbon steel, pickling and passivation for stainless, NDT by method, shop hydrotest, preheat and PWHT
SubcontractPainting, hydrotest and NDT can be priced from a subcontractor's quote instead of in-house work
CurrencyAUD by default, any currency by exchange rate; prices exclude GST and tax
Figure 1.2 The three starting examples, rendered by the tool from its own 3D model. Every spool you enter is drawn the same way.
A SP-101, cooling water
6" carbon steel, tee and vent
Figure 1.2 The three starting examples, rendered by the tool from its own 3D model. Every spool you enter is drawn the same way.
B SP-201, steam
4" carbon steel, bevelled end
Figure 1.2 The three starting examples, rendered by the tool from its own 3D model. Every spool you enter is drawn the same way.
C SP-301, process water
3" stainless 316L, slip-on and blind
Figure 1.2 The three starting examples, rendered by the tool from its own 3D model. Every spool you enter is drawn the same way.

1.5 What it does not cover

www.estineer.com4
ESTINEERPipe Spool Fabrication, User Manual / Chapter 1 Introduction and quick start

1.6 The screen at a glance

Pipe Spool Fabrication12345678910

Figure 1.3 The tool page with the SP-101 example loaded. The numbers match the key below.

1Project: spool tag, line number, service, project name, client, prepared by.
2Line data: material, main size, schedule, flange class, fluid service.
3Components: a one-line summary; the cards themselves are in the Components tab.
4Finish and test: surface finish, NDT, hydrotest, PWHT, preheat; subcontract quotes and workshop rates follow below.
5Title: size, tag and the main line data.
6Result cards: direct cost, indicative price, man-hours, duration.
7Downloads: PDF report, drawings, Excel and Word, with the report, project and check ids.
83D model: drag to rotate, scroll to zoom, right-drag to pan; click a part to select it; Reset view.
9Open 3D in new window: a large view that follows every change; Hide 3D folds it away.
10Tabs: Cost, Components, Cut list, Welds and checks, Schedule, Drawings, Report; drag them into your own order.
Colours in the 3D view. Grey: pipe and fittings. Blue: flanges. Orange: shop welds. Red: welds selected for radiography. Dark red: field welds. Amber: the part you selected.
www.estineer.com5
ESTINEERPipe Spool Fabrication, User Manual / Chapter 1 Introduction and quick start

1.7 Quick start: one spool in five steps

StepWhat to do
1Project. Enter the spool tag and the line number exactly as on the isometric. Project name, client and prepared by go on the report cover; leave them empty and the cover leaves them blank.
2Line data. Choose the material, the main size (the size at the start face), the schedule and the flange class from the line class. Choose the fluid service: it sets the default radiography.
3Components. Open the Components tab. Set the start end and what it connects to. Then add the cards in fabrication order with the buttons at the bottom: pipe, elbow, reducer, branch or olet. Pipe lengths are centre-line lengths from the isometric. Finish with the end type at the finish face. The sketch beside the cards updates as you type; click a part of the sketch to edit its card.
4Finish and test. Choose the surface finish, the hydrotest pressure from the client's line list, and any NDT the client asks for. Leave NDT empty to use the default for the fluid service.
5Rates and price. Check the workshop rates, contingency and markup. Read the result cards, the Cost tab and the alerts; then download the report and drawings.
Start from an example and change it: the tool opens with SP-101. Changing the main size, material or schedule updates every card that follows the main size.

1.8 Preview and the purchased report

On estineer.com the tool is free to use on screen. The cost, man-hours, weights, bill of materials, cut list and weld register are shown in full.

Free preview on screenPurchased report
Cost, price, man-hours, BOM, cut list, weldsFullFull
DrawingsFirst sheet, low resolution, marked PREVIEWFour clean A4 vector sheets
ReportCover page onlyComplete PDF
Excel, Word, MTONot availableLive-formula workbook, editable Word file, MTO in Excel and CSV
Ids and verificationNoneReport id, project id and check code

To buy, press a download button, sign in with a code sent to your email and pay by card. Files are produced on the server after payment, you receive a tax invoice and you can download again for 12 months. Prices and offers are shown on the site at the time of purchase.

The PDF report is the reference document. The Excel and Word files are editable working copies and have no standing on their own.
www.estineer.com6
ESTINEERPipe Spool Fabrication, User Manual / Chapter 2 Inputs

CHAPTER 2Inputs, field by field

The form on the left holds the spool-wide data. The components themselves are cards in the Components tab. Every field is named here exactly as on screen. Where a field has a default, leaving it empty uses the default.

2.1 Project

FieldMeaningDefault / limit
Spool tagThe spool number from the isometric. Printed on every drawing and file name.Up to 24 characters
Line numberThe line the spool belongs to, for example 6"-CW-1001-A1.Free text
ServiceWhat flows in the line. Shown in the title and on the report.Free text
Project name, Client, Prepared byPrinted on the report cover table and the Word cover. Empty fields print blank.Optional

2.2 Line data

FieldMeaningOptions
MaterialSets the pipe, fitting and flange specifications, the filler metal, the material factor on welding hours and the finishes on offer.Carbon steel A106 B seamless; carbon steel A53 B ERW; low-temperature CS A333 Gr 6; stainless 304L; stainless 316L
Main size, NPSThe pipe size at the start face. The size changes along the spool only at a reducer or swage nipple card.NPS ½ to 24
ScheduleWall schedule from the catalogue for the material and size. Fittings follow the pipe wall.As listed for the size
Flange classASME B16.5 pressure class of every flange on the spool.150, 300, 600, 900, 1500
Fluid service (NDT class)Sets the default radiography of butt welds.Normal 5 %; Category D 0 %; Category M 20 %; Severe cyclic 100 %
MaterialPipeFittingsFlangesFiller
CS seamlessA106 Gr BA234 WPBA105E7018 / ER70S-6
CS ERWA53 Gr B ERWA234 WPBA105E7018 / ER70S-6
LTCSA333 Gr 6A420 WPL6A350 LF2 Cl 1E7018-1 / ER70S-6
SS 304LA312 TP304/304LA403 WP304/304LA182 F304/304LER308L
SS 316LA312 TP316/316LA403 WP316/316LA182 F316/316LER316L
www.estineer.com7
ESTINEERPipe Spool Fabrication, User Manual / Chapter 2 Inputs

2.3 Components

The Components tab lists the spool in fabrication order, from the start face to the finish face. Each card is one item. Use the arrows to move a card, the cross to delete it, and the buttons at the bottom to add a card at the end of the list. Click a card, or a part of the live sketch, to open it for editing.

Figure 2.1 The Components tab for SP-101: start end, nine cards, finish end, the add buttons and the live sketch with item numbers.
Figure 2.1 The Components tab for SP-101: start end, nine cards, finish end, the add buttons and the live sketch with item numbers.

Rules that apply to every card

Sizes NPS 1½ and smaller are built with socket-weld fittings (ASME B16.11 Class 3000); larger sizes with butt-weld fittings (ASME B16.9). The tool chooses this from the size; you do not set it.
www.estineer.com8
ESTINEERPipe Spool Fabrication, User Manual / Chapter 2 Inputs
CardFieldsNotes
Start end / Finish endPipe size at the start; end type; Connects to (text on the drawings)End types below
PipeLength, mm (centre line)20 mm to 12,000 mm per straight run
ElbowType: 90° LR (1.5 D), 90° SR (1.0 D), 45° LR; TurnASME B16.9 / B16.11
ReducerType: concentric, eccentric (flat on top or bottom), swage nipple; Outlet size, NPSSwage nipples are MSS SP-95; used automatically where the big end is NPS 1½ or smaller
Tee equal / Tee reducingBranch size; Branch direction; Branch pipe (pipe or nipple 75, 100, 150 mm); Branch length, mm; Branch end; Connects to; Flows in or outBranch length is from the run centre line to the branch end face
Half couplingAs a branch; branch end usually socket weldClass 3000, welded to the run with a hole cut
Weldolet, SockoletAs a branchMSS SP-97; the olet sits on the run pipe
Threadolet, NipoletBranch size and directionThe NPT thread or the 89 mm plain end is the branch end; the connection is by others

End types

EndWhat the tool adds
Weld neck flange (WN)B16.5 weld neck flange, one butt weld, hydrotest end with a test blind
Slip-on flange (SO)B16.5 slip-on flange, two fillet welds; pipe set back by the wall thickness + 3 mm
Socket-weld flange (SW)B16.5 socket-weld flange (NPS 3 and smaller), one socket weld with a 1.6 mm gap
Weld neck + blind (BL)Weld neck flange plus a blind flange, gasket and bolts fitted in the shop
Bevelled end (BE)No item; the end is bevelled for a field weld; hydrotest with a test plug
Plain end (PE)No item; plain end for a field socket weld
CapB16.9 butt-weld cap (or B16.11 socket-weld cap at small sizes)
Up to 12 straight runs and 6 branches per spool. A spool larger than that is usually two spools on the isometric: enter each as its own spool, or use the Pipeline Spool Fabrication tool, which splits a whole line.
www.estineer.com9
ESTINEERPipe Spool Fabrication, User Manual / Chapter 2 Inputs

2.4 Finish and test

FieldMeaningDefault / options
Surface finishCarbon steel: abrasive blast to Sa 2½ plus a paint system. Stainless: pickling and passivation inside and outside.CS: P1 alkyd, P2 epoxy/polyurethane, P3 zinc silicate/epoxy/polyurethane, P5 silicone aluminium, P6 phenolic epoxy (CUI), none. SS: pickle, none
NDT, % of shop weldsSix fields: RT and UT for butt welds; MT and PT for butt welds and for socket, slip-on and branch welds. Empty uses the default.RT default by fluid service; MT on carbon steels only (MT on stainless is refused)
Per-weld NDTIn the Welds tab you can tick the methods weld by weld; those welds are marked as set by you.Optional
Shop hydrotestIncludes the shop hydrotest with test blinds or plugs at every end.On
Test pressure, bar g (client)From the client's line list. Checked against 1.5 × the flange rating at 38 °C.Above 0, at most 400; empty uses 15 bar g with an alert
PWHTPost-weld heat treatment. Auto suggests it for carbon steel walls above 19 mm.Auto, yes, no
Preheat, °CEmpty uses the suggested value (79 °C on carbon steel walls above 25 mm).5 to 300 °C
Insulated in serviceInformation only (insulation is by others); suggests a coating for use under insulation.Off

The tool chooses which welds get NDT: the largest and thickest first, until the percentage is reached. Radiography uses the butt welds of the run; MT and PT on “other” welds cover socket, slip-on and branch welds.

2.5 Subcontract quotes

Painting (or pickling), hydrotest and NDT can each be bought from a subcontractor. Tick the scope and enter the quote in the report currency. The tool then removes the in-house hours and materials of that scope and adds the quote as a cost line “(subcontract)”. Tick it with no amount and the scope is listed under “The price excludes”. Amounts must be zero or more.

www.estineer.com10
ESTINEERPipe Spool Fabrication, User Manual / Chapter 2 Inputs

2.6 Workshop rates

FieldMeaningDefaultAllowed
Currency, Rate per 1 USDReport currency and its exchange rate. Catalogue prices are in USD.AUD, 1.4706Rate above 0
Shop labour, /h all-inFitters, welders, helpers, painters, test crew.110Above 0
Engineering, /h all-inSpool drawing check, weld map, test pack, data book.150Above 0
NDT, /h all-inIn-house NDT technicians.160Above 0
Contingency, %On the direct cost.100 to 100
Markup on cost, %On cost plus contingency.150 to 100
CrewPeople working on the spool at the same time; sets the duration only.21 to 50
Hours / weekWorking hours per week; sets the duration only.381 to 84
A value outside the allowed range stops the run with a message, for example Shop labour rate must be more than zero. The last good result stays on screen, marked as not updated.
Figure 2.2 The Workshop rates section of the form.
Figure 2.2 The Workshop rates section of the form.
www.estineer.com11
ESTINEERPipe Spool Fabrication, User Manual / Chapter 3 How the estimate is calculated

CHAPTER 3How the estimate is calculated

This chapter explains each step from the cards to the price. The tool does not design the pipe: there are no wall-thickness or stress calculations. The calculations are those of a fabrication estimate, and every allowance the tool assumes is printed in the report under “Basis of estimate”.

3.1 Route and fittings

The cards are walked from the start face. Each pipe card moves along the current direction by its centre-line length; each elbow turns the direction; each branch card places a branch at the current point. Fitting dimensions come from the catalogue tables: ASME B16.9 elbows, tees, reducers and caps; ASME B16.11 socket-weld fittings; ASME B16.5 flanges; MSS SP-97 olets and SP-95 swage nipples. The result is a 3D route with every item and every joint located.

3.2 Cut lengths

L centre-line length on the card (start face to tee centre)Y flange lengthC tee centre to endcut length of the pipe piecegapgapface
Figure 3.1 The cut length of a pipe piece is the centre-line length less the parts of the fittings that sit on that length and less the weld gaps.
cut length = L − (take-out of the fitting or flange at each end) − (half the root gap at each bevelled end) pipe to buy per size = sum of cut lengths × (1 + 5 % cutting loss)

Take-outs: elbow centre to end; tee centre to end (run) or centre to branch end; reducer length; flange length Y for weld neck; socket depth less a 1.6 mm gap for socket welds; for slip-on flanges the pipe stops short of the face by the wall thickness + 3 mm. The root gap is 2 mm, so each bevelled end loses 1 mm. A piece shorter than 50 mm gives a warning (hard to weld); a straight run that cannot hold its fittings stops the run.

Example (SP-101, first piece): L = 750 mm from the start face to the tee centre; weld-neck flange Y = 89 mm; 6" tee C = 143 mm; two bevelled ends 2 × 1 mm. Cut length = 750 − 89 − 143 − 2 = 516 mm, as in the Cut list tab.

www.estineer.com12
ESTINEERPipe Spool Fabrication, User Manual / Chapter 3 How the estimate is calculated

3.3 Welds

Butt weld (BW)bevel, root gap 2 mmgap 1.6 mmSocket weld (SW)NPS 1½ and smallerSlip-on flange (SO)two fillet welds, set-backBranch weld (HC / OL)half coupling or olet, hole cut
Figure 3.2 The four weld families the tool counts. Each joint is one line in the weld register with its number, type, size and wall.

Every joint between two items is a weld: pipe to fitting, fitting to fitting, flange to pipe. Branch welds join a half coupling or an olet to the run pipe, with the hole cut included. Field welds at bevelled ends are listed but not priced. The register numbers the shop welds W1, W2 … in fabrication order; the same numbers appear on the 3D view, the isometric and the weld and test record.

3.4 Weights and centre of gravity

3.5 Materials and prices

The material take-off groups the items by size and description: pipe in metres (with the cutting loss), fittings and flanges in each, welding consumables in kg (from the weld size and count), abrasive and paint by area. Prices are catalogue prices in USD multiplied by the exchange rate. A catalogue item with no price is listed under “The price excludes”, never silently priced at zero.

Any material line or any activity can be overridden in the Cost tab: type your own price or hours. The original tool value is kept beside it and the report marks the line as set by you.
www.estineer.com13
ESTINEERPipe Spool Fabrication, User Manual / Chapter 3 How the estimate is calculated

3.6 Man-hours

The man-hours are built activity by activity. Each activity has a quantity, a unit rate from the Estineer man-hour tables and a material factor:

MH = quantity × MH per unit × material factor + extra hours
ActivityQuantity and unitStage
Handlingmetres of pipe by size and scheduleShop
Cutting, bevellingone cut per piece; one bevel per butt-welded endShop
Butt weldsper joint, by size and wallShop
Flange attachmentweld neck (with its butt weld), slip-on (two fillets), socket weldShop
Branch weldshalf coupling or olet, including the holeShop
Socket weldsper joint, Class 3000Shop
Preheat, PWHTper weld, when usedShop
Blind bolting0.1 MH per boltShop
Blasting, paintingoutside area; 0.08 MH per m² per coatShop
Pickling (stainless)inside and outside area, 0.15 MH per m²Shop
QC0.5 MH + 0.05 MH per joint: fit-up, marking, dimensional checkTest
Hydrotestper end: flanged end or plugged end, by sizeTest
NDTper weld examined, by method and sizeNDT
Engineering2 MH + 0.1 MH per weld: drawing check, weld map, test pack, data bookEngineering
MaterialHandling, cuttingWeldingExtra per joint
Carbon steels1.001.000
Stainless 304L, 316L1.201.460.6 h

3.7 NDT and testing

The NDT percentages apply to the count of welds in each group. The tool picks the welds, largest and thickest first, and lists them in the weld register; welds you tick yourself are kept. The hydrotest is priced per end (flanged ends with a test blind, plain or bevelled ends with a test plug). Category M adds a sensitive leak test at half the hydrotest hours. A subcontracted scope replaces these hours by the quote.

www.estineer.com14
ESTINEERPipe Spool Fabrication, User Manual / Chapter 3 How the estimate is calculated

3.8 Cost and price

MaterialsMTO x catalogue price x FXLabourMH x rate by stageSubcontractquotes enteredDirect costrounded up to the next 10x (1 + contingency)x (1 + markup)Indicative pricerounded up to the next 10
Figure 3.3 From quantities to the indicative price.
labour = engineering MH × engineering rate + (shop MH + test MH) × shop rate + NDT MH × NDT rate direct cost = materials + labour + subcontract, rounded up to the next 10 price = direct cost × (1 + contingency) × (1 + markup), rounded up to the next 10

The price excludes GST and tax, transport, site work and anything listed in the red box “The price excludes”.

3.9 Duration

fabrication weeks = (shop MH + test MH + NDT MH) / (crew × hours per week), at least 0.2 drawing approval 0.5 week; procurement 2 weeks (carbon steel) or 3 weeks (stainless); fabrication, NDT and test = fabrication weeks + 0.3; finishing and dispatch 0.5 week duration = total, rounded up to whole weeks

For SP-101: Drawing approval from week 0.0 for 0.5; Material procurement from week 0.5 for 2.0; Fabrication, NDT and test from week 2.5 for 1.0; Finishing and dispatch from week 3.5 for 0.5. Duration 4 weeks. Crew and hours per week change only the duration, never the cost.

3.10 Fabrication checks

CheckRule
Pieces between weldsEach straight run must hold its fittings; a piece under 50 mm gives a warning
TransportThe spool envelope against 12.0 × 2.4 × 2.6 m, a standard truck without a permit
Shop test pressureAt most 1.5 × the flange rating at 38 °C for the class
Heat treatmentPWHT suggested for carbon steel above 19 mm; preheat suggested above 25 mm; confirm with the WPS
MaterialsMT is refused on stainless; LTCS needs impact-tested procedures (noted)

Points the client or the welding engineer must confirm are listed as open items, in amber; they do not stop the estimate.

www.estineer.com15
ESTINEERPipe Spool Fabrication, User Manual / Chapter 4 Outputs

CHAPTER 4Outputs

4.1 Result cards and alerts

Four cards sit under the title: Direct cost (materials + labour), Indicative price (with the contingency and markup used), Man-hours (engineering, shop, NDT and test) and Duration (weeks, with the crew and the empty weight). Alerts appear above the 3D view: yellow points to confirm, red where a check fails or the input was refused.

4.2 The tabs

TabWhat it shows
CostCost build-up by group, the ex-works note, the editable bill of materials and the editable man-hours by activity
ComponentsThe cards in fabrication order and the live sketch (Chapter 2)
Cut listEvery pipe piece: size, schedule, cut length, end preparation, piece mark
Welds and checksThe weld register with type, size, wall and NDT by weld (tick to choose), then the fabrication checks and open items
ScheduleBar chart: drawing approval, procurement, fabrication with NDT and test, finishing and dispatch
DrawingsThe four A4 sheets (section 4.3)
ReportThe estimate report as it will print
Figure 4.1 The Cost tab for SP-101: cost build-up, the ex-works note, the MTO downloads and the start of the editable bill of materials.
Figure 4.1 The Cost tab for SP-101: cost build-up, the ex-works note, the MTO downloads and the start of the editable bill of materials.
www.estineer.com16
ESTINEERPipe Spool Fabrication, User Manual / Chapter 4 Outputs

4.3 Drawings

Four A4 landscape sheets, black on white, generated from the same model as the price. Each carries the Estineer title block, the spool tag and line, a drawing number, the revision and the words FOR REVIEW.

Sheet 1 General arrangement. Plan, front and side views to scale with overall dimensions, the centre of gravity, a 3D view and general notes.
Sheet 1 General arrangement. Plan, front and side views to scale with overall dimensions, the centre of gravity, a 3D view and general notes.
Sheet 2 3D view. The spool in 3D with item numbers and weld numbers.
Sheet 2 3D view. The spool in 3D with item numbers and weld numbers.
Sheet 3 Spool isometric. The fabrication isometric with dimensions, the bill of materials and the cut list. It governs the cut lengths.
Sheet 3 Spool isometric. The fabrication isometric with dimensions, the bill of materials and the cut list. It governs the cut lengths.
Sheet 4 Weld and inspection record. Every weld with its joint, NDT, and columns for PWHT, WPS, welder, date and visual check; then the pressure test record.
Sheet 4 Weld and inspection record. Every weld with its joint, NDT, and columns for PWHT, WPS, welder, date and visual check; then the pressure test record.
www.estineer.com17
ESTINEERPipe Spool Fabrication, User Manual / Chapter 4 Outputs

4.4 The PDF report

The full report opens with a cover page: the 3D picture, the spool, size and class, and a table with project, client, equipment, prepared by, document number and date. The disclaimer is printed once, on the cover. The body follows, with bookmarks, a contents list that links to each section and searchable text:

No.SectionContent
1Estimate summaryDirect cost, price, man-hours, duration, weight; cost build-up
2Spool dataTag, line, service, material, specifications, ends, branches, envelope, weights, test, finish, NDT
3Design basis and fabrication checksStatement that the design is by others; checks and open items
4Bill of materials and MTOItems, quantities, weights, prices
5Cut listPipe pieces and lengths
6Weld registerEvery weld and its inspection
7Labour man-hoursEvery activity with quantity, unit rate, factor and hours
8Basis of estimate: assumptionsEvery allowance the tool used
9ExclusionsWhat the price does not include

The four drawing sheets follow the report in the same PDF. “Drawings only (PDF)” saves the four sheets alone.

4.5 Excel, Word and MTO

FileContent
ExcelSheets Cover, Summary, Materials, Man-hours, Spool data, Cut list, Welds, Checks, Assumptions, Exclusions and MTO. Rates, contingency and markup are named input cells; the cost and price are live formulas, so you can change a rate and see the price move.
WordThe report as an editable document with the cover, the tables and the drawings as pictures.
MTO (Excel, CSV)The material take-off for purchasing: one line per item with quantity, unit, weight and price.

4.6 Ids, check code and verification

Each purchased report carries a report id (ER-XXXX-XXXX) with its revision, a project id (EP-XXXX-XXXX) and a check code. The check code is a fingerprint of the inputs, the engine version and the database. Anyone can confirm a report at estineer.com/verify: the page says whether the report is genuine and when it was issued, without showing the price or the buyer. The ids are printed on the cover, in every page footer, under every drawing frame and in the Excel and Word files.

www.estineer.com18
ESTINEERPipe Spool Fabrication, User Manual / Chapter 5 Worked example

CHAPTER 5Worked example: SP-101

SP-101 is the example the tool opens with: a 6" carbon steel cooling-water spool with a branch tee, two elbows and a 1" vent. Every number in this chapter is produced by the engine when the manual is built, so it matches the tool exactly.

5.1 Inputs

Spool tag / lineSP-101 / 6"-CW-1001-A1
ServiceCooling water
MaterialCarbon steel, ASTM A106 Gr B seamless
Main size, schedule, classNPS 6, 40 / STD, Class 150
Fluid serviceNormal fluid service
Start endWeld neck flange, from 10"-CW-1000 header
Componentspipe 750 mm; tee equal NPS 6 left, branch 450 mm, WN; pipe 750 mm; elbow 90° LR up; pipe 1,200 mm; elbow 90° LR left; pipe 450 mm; half coupling NPS 1 up, branch 250 mm, SW; pipe 450 mm
Finish endWeld neck flange, to E-101 nozzle N1
Finish and testP2 Epoxy / polyurethane; hydrotest 15 bar g; NDT default
Ratesshop 110, engineering 150, NDT 160 AUD/h; contingency 10 %; markup 15 %; crew 2, 38 h/week
SP-101 in the tool's 3D view.
SP-101 in the tool's 3D view.
www.estineer.com19
ESTINEERPipe Spool Fabrication, User Manual / Chapter 5 Worked example

5.2 Geometry, pieces and welds

The route gives an envelope of 1.78 x 1.73 x 1.18 m, inside the 12.0 x 2.4 x 2.6 m truck envelope. The pipe is cut into 6 pieces:

PieceNPSScheduleCut, mmEnds
P16"40 / STD516BE-BE
P26"40 / STD376BE-BE
P36"40 / STD740BE-BE
P46"40 / STD580BE-BE
P56"40 / STD216BE-BE
P61"80 / XS143PE-PE

Piece P1 is worked in section 3.2: 750 − 89 − 143 − 2 = 516 mm. There are 13 shop welds: 10 butt, 1 half coupling, 2 socket. With normal fluid service, radiography is 5 % of the butt welds, which rounds up to 1 weld.

5.3 Materials

Catalogue prices in USD × 1.4706 = AUD. Pipe includes the 5 % cutting loss.

ItemQuantitykgAUD
Pipe 6" sch 40 / STD, ASTM A106 Gr B seamless2.55 m72.0254.27
Pipe 1" sch 80 / XS, ASTM A106 Gr B seamless0.15 m0.51.72
Elbow 90° LR 6"2.00 ea20.4159.00
Flange weld neck RF Class 150 6"3.00 ea32.4462.18
Tee equal 6"1.00 ea16.5128.44
Half coupling 1"1.00 ea0.38.81
Flange socket weld RF Class 150 1"1.00 ea1.014.26
Welding consumables (E7018 / ER70S-6)4.39 kg4.458.13
Abrasive for blasting Sa 2½48.70 kg0.028.66
Paint system P2 Epoxy / polyurethane2.21 m20.040.16
Materials total147.51,155.63

5.4 Weights

Empty 139.6 kg; water 74.1 kg; full of water for the test 213.7 kg. Centre of gravity from the start face: E 1,053 / N 182 / Up 428 mm, shown on the GA drawing.

www.estineer.com20
ESTINEERPipe Spool Fabrication, User Manual / Chapter 5 Worked example

5.5 Man-hours

IDActivityQuantityMH/unitFactorMH
HAND-6Pipe handling in shop NPS 6 sch 40 / STD2.43 m0.20010.49
CUT-6Pipe cutting, machine NPS 6 (one cut per piece)5 ea0.68113.41
BEV-6Pipe bevelling, machine NPS 610 ea0.44514.45
HAND-1Pipe handling in shop NPS 1 sch 80 / XS0.14 m0.10310.01
CUT-1Pipe cutting, machine NPS 1 (one cut per piece)1 ea0.25910.26
BW-6-7.11Butt weld, manual NPS 6 wall 7.11 mm7 joint2.780119.46
HC-1Half coupling NPS 1 welded to run pipe (incl. hole)1 ea1.58011.58
SW-1Socket weld NPS 1 Class 30002 joint0.61411.23
WN-6Weld neck flange attachment NPS 6 Class 150 (incl. butt weld, 3 ea3.860111.58
QCFit-up checks, marking and dimensional inspection1 spool1.15011.15
BLASTAbrasive blasting Sa 2½2.21 m20.10010.22
PAINTPainting P2 Epoxy / polyurethane, 3 coats2.21 m20.24010.53
RTRadiography (RT): 1 of 10 butt welds1 ea1.22011.22
HT-startHydrotest, flanged end (start, NPS 6)1 end1.44011.44
HT-endHydrotest, flanged end (end, NPS 6)1 end1.44011.44
HT-branch 1Hydrotest, flanged end (branch 1, NPS 6)1 end1.44011.44
HT-branch 2Hydrotest, flanged end (branch 2, NPS 1)1 end1.00011.00
ENGSpool drawing check, weld map, test pack and data book1 spool3.30013.30
Total54.2

By stage: engineering 3.30, shop 43.21, NDT 1.22, test 6.47 MH. Engineering = 2 + 0.1 × 13 welds = 3.3 MH.

www.estineer.com21
ESTINEERPipe Spool Fabrication, User Manual / Chapter 5 Worked example

5.6 Cost and price

labour = 3.30 x 150 + (43.21 + 6.47) x 110 + 1.22 x 160 = AUD 6,155.42 materials = AUD 1,155.63 direct cost = 1,155.63 + 6,155.42 = 7,311.05 -> rounded up to AUD 7,320 price = 7,320 x 1.1 x 1.15 = 9,259.80 -> rounded up to AUD 9,260

The tool shows direct cost AUD 7,320 and indicative price AUD 9,260, excluding GST, ex works.

5.7 Schedule

Shop, test and NDT hours 50.9 MH / (crew 2 x 38 h) = 0.67 weeks of fabrication.

StageStarts, weekLasts, weeks
Drawing approval0.00.5
Material procurement0.52.0
Fabrication, NDT and test2.51.0
Finishing and dispatch3.50.5

Duration: 4 weeks from order to dispatch.

5.8 Checks and open items

www.estineer.com22
ESTINEERPipe Spool Fabrication, User Manual / Chapter 6 Limits and questions

CHAPTER 6Limits and questions

6.1 Limits

ItemLimit
SizesNPS ½ to 24; schedules as in the catalogue for each material and size
Route1 to 12 straight runs, each 20 mm to 12,000 mm; up to 6 branches
FlangesClass 150 to 1500; socket-weld flanges NPS 3 and smaller
Test pressureAbove 0 and at most 400 bar g; checked against the flange class
Preheat5 to 300 °C
Commercial inputsRates and exchange rate above 0; contingency and markup 0 to 100 %; crew 1 to 50; 1 to 84 hours per week; edited costs and hours zero or more
TransportSpools larger than 12.0 x 2.4 x 2.6 m are warned: split with a field weld or plan an oversize load

6.2 What is not included

6.3 Messages you may see

MessageWhat to do
Add a pipe before this itemTwo fittings cannot touch: put a pipe card of at least 20 mm between them.
Straight run is too short for its fittingsThe centre-line length is shorter than the fittings on it; check the isometric dimension.
The reducer outlet is the same as the pipe before itChoose a smaller outlet size, or delete the reducer.
Forward / back are for a vertical pipeOn a horizontal pipe turn up, down, left or right.
MT does not work on stainless steelUse PT for surface examination of stainless welds.
Hydrotest pressure not givenEnter the test pressure from the client's line list; 15 bar g is used meanwhile.
Larger than a standard truck loadAdd a field weld (two spools) or allow for an oversize transport.
… must be more than zero / at most …A rate, percentage or crew value is outside the allowed range (Chapter 2).
www.estineer.com23
ESTINEERPipe Spool Fabrication, User Manual / Chapter 6 Limits and questions

6.4 Frequent questions

Does the tool check the pipe for pressure?

No. The design is by others: the wall thickness and class come from the client's pipe class. The tool checks fabrication points only, and says so in the report.

Why is my cut length shorter than the dimension on the isometric?

Isometric dimensions are centre to centre or face to centre. The cut length deducts the fittings and the weld gaps (section 3.2).

Can I use my own prices or hours?

Yes. Type a new value in the bill of materials or the man-hours table in the Cost tab. The report marks the line as set by you and keeps the tool value for reference.

Why does stainless take longer?

Stainless handling and cutting carry a factor of 1.2, welding 1.46, plus 0.6 h per joint for purging and cleaning, and pickling replaces painting.

The price includes transport?

No. The price is ex works: the fabricator's workshop. Transport, unloading and site installation are excluded.

Can two people get the same report from the same inputs?

Yes: the same inputs, engine version and database always give the same numbers and the same check code.

My spool has more than 12 straight runs.

It is usually more than one spool on the isometric. Enter each spool separately, or use Pipeline Spool Fabrication, which splits a whole line into spools.

6.5 Glossary

BE / PEBevelled end for a butt weld / plain end for a socket weld
BW / SWButt weld / socket weld
CoGCentre of gravity
LR / SRLong-radius (1.5 D) / short-radius (1.0 D) elbow
MHMan-hour
MTOMaterial take-off
NDT: RT, UT, MT, PTRadiography, ultrasonic, magnetic particle, dye penetrant
NPSNominal pipe size, inch
PWHTPost-weld heat treatment
SpoolA shop-fabricated piece of piping between field joints
WN / SO / BLWeld neck / slip-on / blind flange
WPSWelding procedure specification
Responsibility. Software output only: must be checked and approved by a qualified engineer. Not engineering advice and not an estimate or quotation.