EstineerManualOpen tool Download PDF
USER MANUAL

Estineer
Atmospheric Storage Tanks

Shop-built atmospheric tanks up to 100 m³: design checks, material take-off, man-hours, price, drawings and reports
www.estineer.com / support@estineer.com
Edition 1, November 2026. Tool version 78, engine 1.64.
Software output only: must be checked and approved by a qualified engineer. Not engineering advice and not an estimate or quotation.
ESTINEERAtmospheric Storage Tanks, User Manual / Contents

CONTENTSManual outline

1Introduction
What the tool is, what it covers, how to read the screen
3
2Quick start
One tank in five steps
8
3Inputs, field by field
Every field: meaning, unit, default, limits, effect
12
4Calculations
Formulas, with figures
18
5Outputs
Cost, schedule, weights, nozzles, drawings, reports, exports, verification
24
6Worked example
10 m³ milk tank, every number shown
29
7Limits and reference
Exclusions, questions, glossary
32
www.estineer.com2
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 1 Introduction

CHAPTER 1Introduction

1.1 What the tool is

The Estineer Atmospheric Storage Tanks tool designs and prices a shop-built atmospheric storage tank from a short datasheet. You describe the tank: what it stores, how big it is, what it is made of, where the nozzles go. The tool then works out the plate thicknesses, checks them against the chosen design standard, lays out the plates and welds, lists every material item, builds the fabrication activities with man-hours, and prices the job.

The same model drives everything you see: the 3D view, the general arrangement and shop drawings, the calculation report, the estimate report, and the Excel and Word files. Change a field and all of them change together, so the drawings can never disagree with the price.

1.2 What goes in and what comes out

YOU ENTER Service, liquid, density, temp.Size by capacity or dimensionsClosures, supports, materialNozzles: size, angle, heightInsulation, agitator, jacketShop rates, markup, contingencyDesign standard, wind dataTemplates fill typical values ESTINEER ENGINE Wall thickness and code checksPlate layout, welds, weightsMaterial take-off (MTO)Activities and man-hoursCost, contingency, markupSchedule and drawingsCatalogue database:weights and prices YOU GET Live 3D model on screenCost, price, man-hours, weeksWeights and nozzle scheduleA4 drawings: GA, nozzles, shopCalculation reportEstimate report with exclusionsPDF, Excel (live), WordSame inputs, same answer
Figure 1.1 What goes in, what happens, what comes out. There is no AI in the number path: every figure comes from the engine and the catalogue database.

The tool runs entirely on engine rules and a catalogue database of weights and prices. It uses no artificial intelligence to produce a number. If you enter the same inputs twice you get the same result, and every report carries a check code that proves which inputs, engine version and database produced it (Chapter 5).

Who it is for

Fabricators who need a fast, traceable cost and a drawing pack for a small tank enquiry; engineers and estimators who need a first-principles check of a quote; and project teams that want a budget price with an honest list of what is not included.

www.estineer.com3
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 1 Introduction

1.3 What the tool covers

ItemCovered
Tank typeShop-built, atmospheric (no internal pressure other than liquid head), full of liquid at design
SizeCapacity 0.5 to 100 m³; inside diameter 0.6 to 4.0 m (road transport limit); shell height 0.5 to 12 m
LayoutsVertical on legs, skirt or slab; horizontal on saddles (Figure 1.2)
Two modesDesigned by this tool: the tool sizes the tank, runs the design checks and issues the calculation book. Designed by the client: you enter the client's thicknesses and details; the tool gives the fabrication estimate and drawings only, and lists any point to raise with the client
ServicesDairy (hygienic, 316L default), sulphuric acid 93 to 98 % (carbon steel), and general liquids; each starts from a template you can change
MaterialsCarbon steel, stainless 304, stainless 316L
Design standardAPI 650 (Annex J, shop-built tanks) or AS 1692 with AS/NZS 1170.2 wind (Australia)
FittingsAny number of nozzles and manways, each on its own card: size, type, angle, height and projection; sanitary, flanged or coupling; a separate nozzle orientation drawing
OptionsInsulation and cladding, agitator (top or side entry), cooling jacket (dimple or half-pipe), one-way sloped bottom, leg rings
CurrencyAUD by default, any currency by exchange rate; prices exclude GST and tax
Figure 1.2 The four layouts the tool handles, rendered by the tool from its own 3D model. Closures can be mixed within each layout; all are shown in Chapter 3.
A Vertical, legs
ellipsoidal top, cone bottom
B Vertical, skirt
dished top and bottom
C Vertical, on slab
cone roof, flat bottom, painted CS
D Horizontal
dished ends, saddles
Figure 1.2 The four layouts the tool handles, rendered by the tool from its own 3D model. Closures can be mixed within each layout; all are shown in Chapter 3.
Usual range and hard limit. Each numeric field has two bands. Outside the hard limit the tool refuses to run and says why (red). Inside the hard limit but outside the usual range it runs and shows a yellow warning asking you to confirm the value. Chapter 3 lists both bands for every field.
www.estineer.com4
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 1 Introduction

1.4 What the tool does not cover

Responsibility. Every output is for review. A qualified engineer must check and approve it before fabrication. The tool gives engineering data and a cost model, not engineering advice and not a quotation. The full statement is printed once, on the cover of the report and on the first page of the Excel and Word files; every drawing is marked FOR REVIEW.

1.5 Where the numbers come from

QuantitySource
Plates, formed heads, legsComputed from geometry and plate stock sizes (no catalogue exists for these); weight from density
Pipe, flanges, fittings, sanitary setsCatalogue database weights and prices; weights are never computed from geometry
Plate pricesDatabase (per kg by material, converted to your currency); you can override rolling with a subcontract rate
Man-hoursBuilt activity by activity from weld lengths, plate counts, fit-up, test and inspection rules
Labour costHours multiplied by your three all-in rates: shop, engineering and NDT
Allowable stresses, minimum thicknessesDeclared assumptions inside the engine, listed in the calculation report

Where a figure is an assumption rather than data, the report says so. Prices are budget level, in 2026 dollars, and stay valid only until a vendor or workshop quote replaces them.

www.estineer.com5
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 1 Introduction

1.6 The screen at a glance

Atmospheric Storage Tanks12345678910

Figure 1.3 The tool page with a milk tank loaded. The numbers match the key below.

1Project: name, tag, template, design by the client or by this tool, standard, liquid, hygienic.
2Size: by capacity or by dimensions; vertical or horizontal.
3Construction: closures, supports, material, plates, density, temperature, wind, finish, insulation. Process options, nozzle cards and workshop rates follow below.
4Title: capacity, service, tag and the main dimensions.
5Result cards: direct cost, indicative price, man-hours, duration.
6Downloads: PDF report, drawings, Excel and Word; the ids shown on screen are registered and become verifiable only at purchase.
7Open items and checks: points the engineer must confirm, in amber; the same list and count as in the report.
83D model: drag to rotate, scroll to zoom, right-drag to pan; click a part to highlight it; open it in its own window.
9Scope notices: ex-works basis and the red list of items you must price from vendor quotations.
10Tabs: Cost, Schedule, Weights, Nozzles, Drawings, Report, Calculations; their order can be changed.
www.estineer.com6
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 1 Introduction

1.7 Preview and the purchased report

The tool is free to use on screen. You can enter any tank, watch the 3D model, read the cost and weights, and see the drawings.

Free preview on screenPurchased report
Cost, price, man-hours, weightsFullFull
DrawingsLow resolution, marked PREVIEW, NOT VALIDClean A4 vector sheets
Report and calculationsCheck summary in full; report and calculation sheet: first page only, the rest is blurredComplete PDF
Excel and WordNot availableLive-formula workbook and editable Word file
Ids and verificationNot issued; ids are registered and verifiable only after purchaseReport id, project id, revision code and check code

To buy, press a download button, sign in with a six-digit code sent to your email, and pay by card. Files are produced on the server only after payment is confirmed, you receive a tax invoice, and you can download again for 12 months. One revision within 24 hours of purchase is free. Prices and offers are shown on the site at the time of purchase.

The PDF report is the reference document. The Excel and Word files are editable working copies and have no standing on their own.

1.8 Conventions used in this manual

1.9 Getting help

Email support@estineer.com with your report id. The check code lets us reproduce your exact result.

www.estineer.com7
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 2 Quick start

CHAPTER 2Quick start

This chapter takes you from an empty page to a priced tank with drawings in five steps. The example is the 10 m³ milk tank that loads when you open the tool. Every field you skip keeps a sensible default, so a first result appears after step 2.

1

Describe the project

Figure 2.1 The Project section.
Figure 2.1 The Project section.

Type a project name. It prints on the report cover only.

Give the tank a tag, for example T-102. It names every drawing and file.

Pick a template: Milk / dairy, Sulphuric acid 93–98 %, General / water, or Custom. A template fills typical values for material, closures, supports, nozzles and finish. Every field stays editable afterwards.

Leave Design by the client unticked if this tool should size the tank and issue the calculations. Tick it when the client has already designed the tank and you only need the fabrication estimate and drawings (Chapter 3).

Choose the design standard and check the stored liquid and hygienic box.

www.estineer.com8
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 2 Quick start
2

Set the size

Figure 2.2 The Size section.
Figure 2.2 The Size section.

Choose By capacity and type the volume in m³. The tool picks a diameter and height that suit road transport and a sensible height-to-diameter ratio.

Or choose By dimensions and type the inside diameter and shell height (or length, for horizontal tanks) in mm.

Pick vertical or horizontal. The result updates as soon as you leave a field.

3

Check the construction

Figure 2.3 The Construction section (top part).
Figure 2.3 The Construction section (top part).

Confirm the top and bottom closures, the supports and the material. A combination the tool does not design (for example a flat bottom on a skirt) gives a plain message instead of a result (Section 3.4).

Set the liquid density, design temperature, corrosion allowance and wind (0 for a tank installed indoors).

Leave Plate thickness on Minimum calculated unless the client has specified thicknesses.

Pick the finish and, if needed, the insulation thickness. Changing the material sets the finish for you (stainless: polish and passivate, CA 0; carbon steel: blast and paint); you can still change both.

www.estineer.com9
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 2 Quick start
4

Add nozzles, options and rates

Open the Nozzles tab to check the openings the template added. Each nozzle is a card: click it to change the mark, service, size, location, type, flange class, angle, position and projection, or press Add nozzle. Grey numbers are the engine's automatic values; type a number to fix your own.

Figure 2.4 Nozzle cards in the Nozzles tab.
Figure 2.4 Nozzle cards in the Nozzles tab.
Figure 2.5 Workshop rates.
Figure 2.5 Workshop rates.

Under Process options choose an agitator and a cooling jacket if the service needs them.

Under Workshop rates set the currency and its rate to the US dollar, your three all-in hourly rates (shop, engineering, NDT), contingency, markup, crew size and hours per week. These change cost and duration, never the design.

www.estineer.com10
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 2 Quick start
5

Read the result and download

The result panel shows the title line, four result cards and the download buttons. Read the amber open items and checks first: they are the points an engineer must confirm. Then look through the tabs (Chapter 5).

Figure 2.6 Title line and the four result cards.
Figure 2.6 Title line and the four result cards.

Download PDF report gives the complete report: cover, estimate, calculations and all drawings in one file. Drawings only, Export Excel and Export Word give the other files. On the website, a download asks you to sign in with an emailed code and pay for the report; the files are then made on the server.

2.1 Checklist before you send a price

The same inputs always give the same result. Save the PDF report with your offer: its check code proves which inputs, engine version and database produced it.
www.estineer.com11
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 3 Inputs, field by field

CHAPTER 3Inputs, field by field

Fields are listed in screen order. Limits give the hard limit (outside it the tool stops and says why, in red) and, in brackets, the usual range (outside it the tool runs but asks you to confirm, in yellow). A dash means the field is a choice, not a number.

3.1 Project

FieldWhat it means and what it changesDefaultLimits
Project namePrinted on the report cover. No effect on the design or price.empty–
TagEquipment number. Names the drawings (for example ESTN-T-102-01) and the files.T-102–
TemplateMilk / dairy, Sulphuric acid 93–98 %, General / water, or Custom. Fills typical material, closures, supports, nozzles, density, temperature and finish. Custom keeps what you typed.Milk / dairy–
Design by the clientTicked: you enter the client's thicknesses and sizes; the tool keeps them, prices the fabrication and draws the tank, and lists failed background checks as points to raise with the client. No calculation book is issued. Unticked: the tool sizes the tank and issues the calculations.unticked–
Design standardAPI 650 (Annex J, shop-built tanks, selected methods) or AS 1692 with AS/NZS 1170.2 wind. Sets minimum thicknesses, joint efficiency, wind method and the code references in the report.API 650–
Stored liquidName of the product, printed on drawings and reports.by template–
Hygienic designSelf-draining bottom, polished product surfaces, sanitary clamp fittings, continuous welds ground flush inside. Adds polishing and passivation work.on for dairy–

3.2 Size

FieldWhat it means and what it changesDefaultLimits
By capacity / By dimensionsCapacity: the tool chooses the diameter and height. Dimensions: you give them.By capacity–
Capacity, m³Geometric volume to the top of the shell.100.5 to 100
OrientationVertical or horizontal (Figure 1.2).Vertical–
Inside diameter, mmShown with By dimensions. Road transport limits it to 4 m.2000600 to 4000
Shell height / length, mmVertical: shell height. Horizontal: length between tangent lines.by capacity500 to 12000; H/D 0.5 to 4, L/D 1 to 6
www.estineer.com12
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 3 Inputs, field by field

3.3 Closures

FieldWhat it means and what it changesDefaultLimits
Top / roofTorispherical, 2:1 ellipsoidal, cone, dome, flat or open top (Figure 3.1). An open top moves roof nozzles to the upper shell and drops the vent and manway.by template–
Cone roof angle, °Slope of a cone roof from horizontal. API 650 asks for 9.5 to 37°; outside it the check is NOT OK.105 to 45
BottomFlat, flat sloped one way, torispherical, 2:1 ellipsoidal or cone (Figure 3.2). Formed and cone bottoms drain to a centre outlet.by template–
Bottom slope, °For the sloped flat bottom: the plate is tilted one way, low side at 90°, to a side outlet.21 to 10
Cone bottom angle, °Slope of a cone bottom from horizontal. A steeper cone drains better and needs a thinner plate and a smaller junction ring.155 to 60
Figure 3.1 Top closures, from left: torispherical, 2:1 ellipsoidal, cone, dome, flat, open top.
Torispherical
2:1 Ellipsoidal
Cone
Dome
Flat
Open top
Figure 3.1 Top closures, from left: torispherical, 2:1 ellipsoidal, cone, dome, flat, open top.
Figure 3.2 Bottoms on legs, from left: flat, flat sloped one way, torispherical, 2:1 ellipsoidal, cone.
Flat
Sloped one way
Torispherical
2:1 Ellipsoidal
Cone
Figure 3.2 Bottoms on legs, from left: flat, flat sloped one way, torispherical, 2:1 ellipsoidal, cone.
www.estineer.com13
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 3 Inputs, field by field

3.4 Supports and plates

FieldWhat it means and what it changesDefaultLimits
SupportsLegs, skirt or on slab (horizontal tanks: saddles). Changes the support design, the wind and overturning checks, and the anchors. Legs, rings, pads, skirt, base ring, chairs and bolts are sized on the final weight. Not designed (plain message instead of a result): a flat or sloped bottom on a skirt, and a formed or cone bottom on a slab. A flat bottom on legs needs a beam grid under the plate; a dished or cone bottom is the usual choice.by template–
Leg attachmentPads plus two support rings (calculated by the tool) or plain pads (local shell stress to be checked by the engineer, WRC 537 or FEA).Pads + 2 rings–
Number of legs, Leg pipe sizeShown in Design by the client mode, vertical tanks on legs. Auto lets the tool choose from the load and slenderness.auto3, 4, 6 or 8 legs; NPS 2 to 8
Skirt thickness, mmShown in Design by the client mode on a skirt.auto3 to 20
MaterialSS316L, SS304 or carbon steel (CS). Sets allowable stress, plate prices, welding process and finish options.by template–
Plate stock, W × L mmPlate size the shell is cut from. Sets the number of courses, plates per course and the weld length.1500 × 6000 SS, 1800 × 6000 CS–
Rolling and formingIn our shop, or Subcontractor. Subcontracted rolling is shown as a vendor item unless you type the roller's rate per kg.In our shop–
Plate thicknessMinimum calculated: the tool selects the next stock plate above every requirement. Custom: you type shell, bottom and roof thicknesses; a value below the minimum fails its check and the minimum is used instead (Design by the client keeps it).Minimum calculated–
Corrosion allowance, mmAdded to every pressure-part thickness and checked on nozzle and manway necks.by template0 to 6 (up to 3)
www.estineer.com14
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 3 Inputs, field by field

3.5 Service conditions and finish

FieldWhat it means and what it changesDefaultLimits
Liquid density, kg/m³Sets the hydrostatic load. Water (1000) is used if the product is lighter, so the hydrotest also governs.by template500 to 2000 (700 to 1850)
Design temperature, °CReduces the allowable stress and modulus of stainless steel above ambient.by template−20 to 260 (0 to 95)
Wind, km/h (0 = indoor)API 650 basic wind speed. With AS 1692: wind region, terrain category and return period replace it.0 dairy, else 1600 to 250
FinishPolish, pickle and passivate (stainless) or blast and paint. Changing the material sets it (and CA 0 for stainless); a painted stainless tank or a CA above 1 mm on stainless gives a yellow warning.by material–
Insulation, mm; Insulation extentHygienic tanks: PU foam with stainless cladding; other tanks: mineral wool with aluminium cladding. Full tank or shell only. Adds weight, cost and man-hours.00 to 200 (25 to 100)

3.6 Process options

FieldWhat it means and what it changesDefaultLimits
AgitatorNone, top entry (centre) or side entry. The tool adds the mounting nozzle and pad, checks the mount and lists the agitator itself as a vendor item. Vertical tanks only.top for dairy–
Agitator power, kWSets the nozzle size and the mounting check.0.750.18 to 15 (0.25 to 5.5)
Cooling jacketNone, dimple plate or half pipe. Adds jacket plate or pipe, welds, a separate jacket pressure test and its connections. Vertical tanks only.None–
Jacket height, % of shellShare of the shell height covered by the jacket. The jacket stays clear of the leg pads, support rings and lifting lugs; if less is free, the tool warns and uses what fits, and stops below 300 mm. Shell nozzles in the jacket zone get cut-outs (warning).7520 to 95 (40 to 90)
www.estineer.com15
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 3 Inputs, field by field
Figure 3.3 Options, from left: 75 mm insulation with cladding, dimple jacket with top agitator, side-entry agitator.
Figure 3.3 Options, from left: 75 mm insulation with cladding, dimple jacket with top agitator, side-entry agitator.

3.7 Nozzles

Each opening is a card in the Nozzles tab. Marks starting with M are manways. Empty fields take the engine's automatic value, shown in grey.

FieldWhat it means and what it changesDefaultLimits
Mark, ServiceTag and duty, for example N2 Outlet. The service picks the default type and flange.by template–
SizeNPS 1/2 to NPS 24.by service–
LocationTop / roof, shell high, shell, shell low, or bottom.by service–
Type, Flange classBy service (auto), slip-on, weld neck, clamp or coupling; Class 150 or 300.auto–
Angle, °Plan angle clockwise from north. Horizontal tanks: 0 = top, 90 = side, 180 = bottom, viewed from the left end.auto, clear of seams and lugs0 to 360
Position, mmShell: elevation above the shell bottom. Roof: distance from the centre. Horizontal: distance from the left tangent line.autoinside the shell or roof
Projection, mmFrom the shell or head outside to the flange face.by size50 to 500
www.estineer.com16
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 3 Inputs, field by field

3.8 Workshop rates

FieldWhat it means and what it changesDefaultLimits
Currency, Rate per 1 USDCurrency of every cost and price. The database is in US dollars; the rate converts it.AUD, 1.4706> 0
Shop labour, Engineering, NDT (per hour, all-in)Your three all-in labour rates. Man-hours are multiplied by the rate of their group.110 / 150 / 160 AUDequivalent 10 to 300 USD/h
Contingency, %Added to the direct cost for unknowns.100 to 50 (5 to 25)
Markup, %Profit on cost: price = cost × (1 + contingency) × (1 + markup), rounded up to the next 50.150 to 50 (5 to 30)
Crew, Hours / weekWorkshop crew and working week. Change the duration only.4, 381 to 20; 20 to 84 (36 to 60)

3.9 Editing the result

In the Cost tab every material cost and every activity's man-hours can be typed over. Press Enter to apply. Edited values are marked in the report, and a value more than 50 % away from the tool's figure raises a yellow warning.

What the tool never lets you do. It never accepts a plate thinner than the calculated minimum without a failed check, never prices a vendor item it has no data for (it lists it in red instead), and never changes your typed nozzle positions; it warns when they clash with a seam, a lug or another nozzle.
www.estineer.com17
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 4 Calculations

CHAPTER 4Calculations

The calculation report follows the order below. Each row shows the formula, the numbers put into it and the result, so an engineer can check it by hand. The methods are the selected methods of the chosen standard for shop-built atmospheric tanks; where the tank is outside a standard's scope (for example a suspended bottom on legs), the report says so and states the method used.

4.1 Design data

Tag, service, standard, orientation, material, inside diameter, shell height, closures, geometric capacity, design liquid level, specific gravity G = max(1.0, density / 1000), design pressure (atmospheric, full of liquid), design temperature, corrosion allowance CA, joint efficiency E = 0.85 (spot radiography) and the allowable design stress Sd.

4.2 Shell thickness

COURSE 1COURSE 2DESIGN LIQUID LEVEL0.3 mH1 (course 1)H2D (inside)ONE-FOOT METHOD (API 650)For each course, H is the height fromthe bottom of the course to the designliquid level. Flat bottom: stress point0.3 m above the course bottom.td = 4.9 D (H-0.3) G / (Sd E) + CAtt = 4.9 D (H-0.3) / (St E)Adopted: next stock plate≥ max(td, tt, minimum nominal)D in m, H in m, Sd and St in MPa, t in mm
Figure 4.1 Shell courses and the design liquid level. The lowest course carries the largest head.
QuantityFormula
Design thickness td4.9 D (H - h0) G / (Sd E) + CA
Test thickness ttstainless: 4.9 D (H + x - h0) / (St E), AS 1692 x = 1 m; carbon steel: AS 1692 with Sd, API 650 hydrotest check only
Reduction h00.3 m only where a flat (or one-way sloped) bottom restrains the shell foot; 0 for formed and cone bottoms and for horizontal tanks
Minimum nominalstandard table for the diameter (+ CA where the standard requires)
Check (corroded)4.9 D (H - h0) G / (tn - CA) ≤ Sd E
www.estineer.com18
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 4 Calculations

4.3 Heads, bottom and roof

JUNCTION COMPRESSION RING(WHEN REQUIRED, DETAIL W2)OUTLET AT APEXbcone slope from horizontal = 90 - bDP = rho g H_totalth = P D / (2 cos b Sd E) + CAQ = P R / 2 x tan bA_req = Q R / (0.6 Sd)
Figure 4.2 Cone bottom. b is the half apex angle; H_total is measured from the apex, so it includes the cone depth.
QuantityFormula
Pressure at the lowest pointP = max(density, 1000) × 9.81 × H_total; AS 1692: the larger of the product to the design level and water to the top plus 1 m (test head of clause 2.8.2)
Formed bottom or headth = P D M / (2 Sd E) + CA, then × 1.1 forming thinning; M = 1.54 torispherical, 1.0 ellipsoidal
Formed head minimumstandard minimum + CA, and t - CA ≥ 0.002 L (L = D torispherical, 0.9 D ellipsoidal); horizontal heads at most one plate step thinner than the shell
Cone bottomth = P D / (2 cos b Sd E) + CA, not less than the minimum + CA
Cone/shell junctionQ = P R / 2 tan b ; A_req = Q R / (0.6 Sd) ; A_av = 0.78 √(R t) t for cone and shell, corroded; ring added for the shortfall
Flat bottomCS: 6 mm + CA ; stainless: corroded thickness ≥ 5 mm
Top head or roofno hydrostatic load: minimum + CA; cone, flat and dome roofs checked for self-weight and roof load

Automatic selection uses the same total head as the printed check, so a selected bottom always passes its own calculation. A thickness you type below the requirement is not used: the tool keeps the required thickness and marks the check NOT OK. Only in Design by the client mode is the typed thickness kept, as a point to raise with the client.

www.estineer.com19
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 4 Calculations

4.4 Nozzles, manways and reinforcement

dA3: PAD (HATCHED)A1: EXCESS SHELLA2: NECK WITHIN 4 tnSHELL
Figure 4.4 Area replacement for a shell opening. The area removed (d × t_req) must be replaced by A1 + A2 + A3.
QuantityFormula
Shell openings > NPS 2A_req = d × t_req (t_req at the opening's own liquid head) ; A_av = d (tn - CA - t_req) + 2 × min(4 t_neck, 8 tn) (t_neck - CA) + pad
NPS 2 and smallerexempt from reinforcement (API 650 5.7.2.1); neck wall still checked
Openings in a formed or cone bottomarea replacement at the pressure of the lowest point, plus neck hoop stress P (OD - t) / (2 (t - CA)) ≤ Sd
Openings in a top head or roofabove the liquid: no pressure; local load check on the parent plate
Horizontal tanksevery opening is below the liquid (design level = full diameter); head at the opening's lowest edge = R (1 - cos a) + OD/2 |sin a|
Neck wallsafter 12.5 % mill tolerance and CA ≥ 1.5 mm; manway necks keep their table minimum after CA
Shell manway cover and ringstandard table entered with the equivalent head = liquid height × max(G, 1); above 8 m the table thickness is scaled by √(head / 8) and marked open for the engineer

4.5 Weights and centre of gravity

Empty, operating (normal fill), full of product to the design level and hydrotest (full of water) weights, each from the material take-off. Centres of gravity are estimated from part elevations and reported for information; the weights size the supports and the lifting lugs.

www.estineer.com20
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 4 Calculations

4.6 Wind

FwarmSUPPORT BASE (LEG FEET)LEGSFwarmSUPPORT BASE (UNDER BASE RING)SKIRTskirt areaincluded
Figure 4.3 Wind force and the support base. Every overturning moment, including those for the skirt, base ring and anchors, is taken about the support base.
QuantityFormula
API 650shell 0.86 kPa and roof uplift 1.44 kPa at 190 km/h, scaled by (V / 190)²
AS/NZS 1170.2Vdes = VR (× 1.05 region C, 1.10 region D, for R of 50 years or more; regional speed confirmed where the map shows subregions) Md Mz,cat, not less than 30 m/s ; q = 0.6 Vdes² ; shell Cfig 0.63 ; roof Cp,e mean 0.65
ForceFw = Pws × projected area (for a skirt, down to the base ring)
Moment at the support baseMw = Fw × arm (+ roof uplift moment, vertical tanks)
www.estineer.com21
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 4 Calculations

4.7 Supports

QuantityFormula
Legs, axialKL = 2 × free length ; λ = KL / (r π) √(fy / E) ; P_all = A fy / (1.67 (1 + λ²))
Legs, windP_ot = 4 Mw / (n Dc) ; P / P_all + fb / (0.66 fy) ≤ 1 ; uplift when empty > 0 needs anchored base plates
Leg padspad length chosen from 300 to 1000 mm so that the leg-to-pad welds and the shell shear pass; the legs, rings and drawings use the same length
Leg rings and weldsrings at the top and bottom of the pad; radial couple F = Pd (e + t/2) / hr; ring bending, leg-to-ring welds, ring-to-shell welds (stitch 1/3, 1/2 or continuous), shell bearing; anchor bolts M16 to M30 from the uplift
SkirtW / A + Mw / Z ≤ allowable with the section reduced at the access opening and yield at temperature; skirt-to-head weld; base ring and anchor bolts increased until bearing, ring bending and bolt stress pass
Flat bottom on legsplate between beams; beams for bending, deflection L/360, wall ≥ 3 mm, compact flange and web, and web shear at the end clips
Final weightsupports are sized on the finished empty weight; if jacket, insulation or welds make the tank heavier than the sizing weight, the whole model is run again
Saddles (horizontal)Saddle stress analysis: longitudinal bending, shear, horn stress, wear plate edge, ring compression at the saddle and, when A ≤ R/2, head shear and head stress; wear plate b + 1.56 √(R t) wide; the shell is thickened until all pass, otherwise the tool stops

4.8 Lifting lugs and anchorage

QuantityFormula
Lug load2 × empty weight shared by the lugs, sling at 60°, safety factor 4 on ultimate
Lug platenet tension, tear-out and pin bearing
Lug-to-pad weldsfull moment from both components: vertical tank M = Fv b/2 + Fh |h/2 - a|; horizontal tank M = Fh (b - a); combined stress ≤ 0.6 Fe / 4; the lug size is raised until it passes
Pad-to-shell weld and shellweld group with the moment including the pad thickness; shell shear around the pad; local shell bending left open for the engineer
Overturning, tank on slabresisting weight = corroded shell and roof only (no bottom, no liquid); anchor chairs and bolts chosen from 4 × M24 up to 8 × M30
www.estineer.com22
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 4 Calculations

4.9 Agitator, jacket and hydrotest

QuantityFormula
Agitator mountnozzle and pad sized from the power; weld and wall checked on the corroded wall; local loads (WRC 107 / 297 or FEA with the vendor's loads) open for the engineer
Cooling jacketplate or half pipe sized for 3 bar g, panel stress on the corroded shell; separate jacket pressure test. The jacket is pressure equipment: AS 1210 (dimple plate by clause 3.16.6, half pipe by clause 3.23), hazard level and registration by the engineer
Hydrotestfull of water to the top of the shell (AS 1692: plus 1 m); shell stress 4.9 D (H - h0) / tn ≤ St E ; 4 h hold, no leaks

4.10 Inspection and NDT basis

Every weld in the weld register carries its own inspection requirement, and the priced activities count from the register:

4.11 From model to price

QuantityFormula
MaterialΣ take-off items: plates from geometry and stock size, catalogue items from the database
Man-hoursΣ activities: quantity × crew × hours per unit × modifiers (material, position, thickness) × 1.2 allowance
Labourengineering MH × engineering rate + shop MH × shop rate + NDT MH × NDT rate
Direct costmaterial + labour, rounded up to the next 50
Indicative pricedirect cost × (1 + contingency) × (1 + markup), rounded up to the next 50
Durationengineering and approval, procurement, shop man-hours / (crew × hours per week), testing, dispatch
Every check ends as OK, NOT OK, SPECIFIED (met by the specification, no number), N/A or OPEN (for the engineer). The report cover states how many checks pass, how many are not OK and how many are open.
www.estineer.com23
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 5 Outputs

CHAPTER 5Outputs

The result panel has four result cards and seven tabs. Tabs can be put in your own order with Arrange tabs.

5.1 Result cards

Direct costMaterial plus labour at your rates, rounded up to the next 50. Ex-works, excluding vendor items listed in red.
Indicative priceDirect cost with contingency and markup, before tax.
Man-hoursTotal, split into engineering, shop and test (NDT, hydrotest, dimensional).
DurationWeeks from order, for your crew and working week.

5.2 Cost

Figure 5.1 Cost tab: build-up, scope notices and the editable material list.
Figure 5.1 Cost tab: build-up, scope notices and the editable material list.

The build-up groups material and labour lines. Below it, every material item and every activity can be edited (Section 3.9). Site installation is shown separately and is not in the price.

www.estineer.com24
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 5 Outputs

5.3 Schedule and weights

Figure 5.2 Schedule tab: five stages from order to dispatch.
Figure 5.2 Schedule tab: five stages from order to dispatch.
Figure 5.3 Weights tab: empty, operating, full, hydrotest, weld length and plate layout.
Figure 5.3 Weights tab: empty, operating, full, hydrotest, weld length and plate layout.

5.4 Nozzles

The nozzle cards (Section 3.7) with a live plan and front elevation. Click a card or a balloon to highlight the nozzle in the 3D model. The same layout prints as the Nozzle orientation drawing.

5.5 Calculations

The design status (calculated checks passed and open items), the notes from the engine, and the full calculation sheet in the order of Chapter 4.

www.estineer.com25
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 5 Outputs

5.6 Drawings

Figure 5.4 Drawings tab. On screen the sheets are low-resolution previews marked PREVIEW, NOT VALID.
Figure 5.4 Drawings tab. On screen the sheets are low-resolution previews marked PREVIEW, NOT VALID.
SheetContent
01 GA viewsPlan, elevation, isometric, nozzle schedule, design data and notes
01-2 GA schedulesNozzle schedule, design data and notes of the GA at a readable size
NO Nozzle orientationOrientation plan (or end view), developed shell with seams, pads and openings, nozzle table
S01 Shell developmentPlates, seams and openings laid flat with dimensions
S02 Cutting and material listPlate cutting plan and the full material list
S03 to S05 Weld detailsW1 to W6: shell seams, bottom to shell, nozzle neck, flange, supports, lug
S06 Welding notesProcesses, consumables, preparation, inspection and finish notes
S07 Weld scheduleEvery registered weld: joint, type, size, length, process and NDT
S08 Nozzle detail scheduleNeck, flange or ferrule, pad, projection and weld for each opening

Sheets are A4, numbered with the tag (for example ESTN-T-102-S07) and marked FOR REVIEW.

www.estineer.com26
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 5 Outputs

5.7 Report

Figure 5.5 Report tab: the cover of the estimate and engineering report.
Figure 5.5 Report tab: the cover of the estimate and engineering report.

The PDF report holds the cover (with the 3D picture, ids and the full responsibility statement), the estimate (basis, cost build-up, exclusions, schedule, inputs to confirm), the calculation report and all drawing sheets, with bookmarks and a linked contents list.

www.estineer.com27
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 5 Outputs

5.8 Files

FileWhat it is
PDF reportThe reference document: estimate, calculations and drawings. Searchable text, bookmarks.
Drawings (PDF)The A4 drawing set on its own.
ExcelLive-formula workbook: inputs as named cells, material and activity tables, cost build-up. Change a rate and the price follows. A working copy only.
WordEditable report text for your own offer or notes. A working copy only.
The Excel and Word files state that the PDF report is the basis and that they have no standing on their own.

5.9 Ids and verification

Project idEP-XXXX-XXXX, one per tank tag.
Report id and revisionER-XXXX-XXXX Rev A, one per set of inputs; each issued revision also gets a revision code RV-XXXX-XXXX.
Check codeXXXX-XXXX, made from the inputs, the engine version and the database. The same inputs always give the same code.

The ids are printed on the cover, the page footers, under every drawing frame, and in the Excel and Word files. Anyone can enter a report id at estineer.com/verify to see whether it is genuine, its date and the tank; prices and the buyer are never shown.

5.10 On screen and after purchase

The screen shows every number for free. Drawings on screen are low-resolution and marked PREVIEW, NOT VALID; the Report tab shows the cover only, and the Calculations tab shows the design status, check summary and notes with the full calculation sheet blurred after its first page. After purchase the files are clean and complete, and can be downloaded again for 12 months.

www.estineer.com28
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 6 Worked example

CHAPTER 6Worked example

The 10 m³ milk tank T-102 is the tank that loads when the tool opens. Every number below comes from the engine with the inputs in Section 6.1, engine version 1.64; you can reproduce them on screen.

6.1 Inputs

FieldValue
Template, liquidMilk / dairy, milk, hygienic
Capacity10 m³, vertical
Closures, supports2:1 ellipsoidal top, 15° cone bottom, 4 legs with pads and 2 support rings
Material, finishSS316L, polish, pickle and passivate
Density, temperature, CA, wind1030 kg/m³, 95 °C, 0 mm, indoor
Agitator, jackettop entry 0.75 kW, none
NozzlesN1 inlet, N2 outlet, N3 CIP spray ball, N4 vent, N5 level, N6 temperature, N7 sample, M1 manway NPS 18
Ratesshop 110, engineering 150, NDT 160 AUD/h; contingency 10 %, markup 15 %; crew 4, 38 h/week

6.2 Geometry the tool chose

ItemValue
Inside diameter × shell height2,050 × 2,950 mm
Geometric capacity10.04 m³
Shell5 mm, 2 courses of 2 plates from 1500 × 6000 stock
Design liquid level from the apex3,225 mm
Cone bottom / top head5 mm / 5 mm
Legs4 pipe legs NPS 2-1/2, 1,175 mm long
www.estineer.com29
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 6 Worked example

6.3 Design checks

The calculation report gives the full working; the summary is below.

CheckValueLimitResult
Shell hoop stress ratio (corroded)0.061.00OK
Cone bottom thickness5.00 mm1.17 mmOK
Cone/shell junction area819.72 mm2819.72 mm2OK
N2 bottom opening reinforcement335.62 mm24.15 mm2OK
M1 manway in top head (local load)0.28 MPa58.83 MPaOK
Leg axial (full of product to design level)0.681.00OK
Leg axial + bending (full of product + wind)0.681.00OK
Leg-to-pad fillet welds17.55 MPa144.00 MPaOK
Shell shear at leg pad9.55 MPa58.83 MPaOK
Leg support ring bending83.62 MPa97.08 MPaOK
Leg-to-ring welds7.92 MPa144.00 MPaOK
Ring-to-shell stitch welds32.90 MPa144.00 MPaOK
Shell bearing at the lower leg ring11.20 MPa132.38 MPaOK
Leg uplift, empty + wind (no anchors needed)-3.29 kN0.00 kNOK
Lifting lug 120 x 10 plate and weldsOKSF 4 on ultimateOK
Lug pad weld and shell shear0.131.00OK
Local shell bending at lifting lugsnot calculatedengineeropen
Agitator mountOKpad on wallOK
Hydrotest shell stress5.93 MPa131.75 MPaOK

Example by hand, cone bottom: P = 1030 × 9.81 × 3.225 = 32.6 kPa; th = 0.0326 × 2,050 / (2 × cos 75° × 130 × 0.85) = 1.17 mm, so the 5 mm minimum thickness of the standard governs and the adopted plate is 5 mm.

www.estineer.com30
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 6 Worked example

6.4 Cost and price

LineMHAUD
Plates, heads and structural14,758
Nozzles, flanges and manway3,573
Supports, lugs and access1,723
Agitator mounting and cooling jacket237
Consumables, surface treatment and finishing724
Engineering, calculations and drawings44.46,660
Shop fabrication222.524,470
NDT (visual, radiography, penetrant)38.76,188
Hydrotest and dimensional inspection14.41,585
Material + labour319.959,917
Direct cost (rounded up to 50)59,950
Contingency 10 %, markup 15 %× 1.10 × 1.15
Indicative price (rounded up to 50)75,850

Check: 59,950 × 1.10 × 1.15 = 75,837, rounded up to 75,850 AUD.

Not in the price: Agitator top-entry 0.75 kW, about 40 rpm, Instrument LT-1 (LT) on N5, Instrument TT-1 (TT) on N6. Transport, unloading and site installation are also excluded (ex-works).

6.5 Weights and duration

ItemValue
Empty / operating / full / hydrotest1,341 / 11,164 / 11,681 / 11,380 kg
Weld length66 m
Duration7 weeks from order: engineering 1.5, procurement 3 (starts in week 1, overlapping engineering), fabrication about 1.5, testing 1, dispatch 0.5
www.estineer.com31
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 7 Limits and reference

CHAPTER 7Limits and reference

7.1 Limits

www.estineer.com32
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 7 Limits and reference

7.2 Questions

Why is my thickness larger than the formula gives?

Small tanks are usually governed by the minimum thickness of the standard, the next stock plate, or a support or nozzle check, not by the hoop stress. The calculation report shows which.

Why does the run stop with a red message?

A value is outside its hard limit (Chapter 3), or the combination is one the tool does not design (Section 7.1). The message says what to change.

A check says NOT OK. What now?

With Minimum calculated thickness the tool fixes most checks itself. A NOT OK usually follows a value you typed (a custom thickness, a nozzle position) or a client design. Change the input, or raise the point with the client.

Why is the agitator not in the price?

It is a vendor item. The tool prices its nozzle, pad and installation, and lists the agitator in the red box so you add the vendor's quotation.

Can I change a man-hour or cost figure?

Yes, in the Cost tab. Your edits are marked in the report, and large changes raise a warning.

Will the same tank give the same price tomorrow?

Yes, while the engine version and database stay the same. The check code changes when either changes.

Who is responsible for the design?

The engineer who checks and approves it. The tool gives engineering data and a cost model, not engineering advice and not a quotation.

www.estineer.com33
ESTINEERAtmospheric Storage Tanks, User Manual / Chapter 7 Limits and reference

7.3 Glossary

Annex JAPI 650 annex for shop-built tanks
CACorrosion allowance, added to thicknesses
CourseOne ring of shell plates
Direct costMaterial plus labour, before contingency and markup
EJoint efficiency, 0.85 for spot radiography
Ex-worksPrice at the fabricator's workshop, before transport
GDesign specific gravity, at least 1.0
GAGeneral arrangement drawing
HydrotestTest full of water before dispatch
MarkupProfit added on cost
MHMan-hours
MTOMaterial take-off: every item with weight and cost
NDTNon-destructive testing: VT visual, RT radiography, PT penetrant, MT magnetic particle
NPSNominal pipe size
Open itemA point the engineer must confirm
PadReinforcing plate around an opening or under a leg or lug
Sd, StAllowable design and hydrotest stress
SPECIFIEDA requirement met by the specification, with no number to check
Support baseThe plane the overturning moment is taken about: leg feet, or under the skirt base ring
TagEquipment number, for example T-102
Vendor itemBought-in item priced from a quotation, not by the tool

7.4 Support

Email support@estineer.com with your report id and check code.

www.estineer.com34