| 1 | Introduction What the tool is, what it covers, how to read the screen | 3 |
| 2 | Quick start One tank in five steps | 8 |
| 3 | Inputs, field by field Every field: meaning, unit, default, limits, effect | 12 |
| 4 | Calculations Formulas, with figures | 18 |
| 5 | Outputs Cost, schedule, weights, nozzles, drawings, reports, exports, verification | 24 |
| 6 | Worked example 10 m³ milk tank, every number shown | 29 |
| 7 | Limits and reference Exclusions, questions, glossary | 32 |
The Estineer Atmospheric Storage Tanks tool designs and prices a shop-built atmospheric storage tank from a short datasheet. You describe the tank: what it stores, how big it is, what it is made of, where the nozzles go. The tool then works out the plate thicknesses, checks them against the chosen design standard, lays out the plates and welds, lists every material item, builds the fabrication activities with man-hours, and prices the job.
The same model drives everything you see: the 3D view, the general arrangement and shop drawings, the calculation report, the estimate report, and the Excel and Word files. Change a field and all of them change together, so the drawings can never disagree with the price.
The tool runs entirely on engine rules and a catalogue database of weights and prices. It uses no artificial intelligence to produce a number. If you enter the same inputs twice you get the same result, and every report carries a check code that proves which inputs, engine version and database produced it (Chapter 5).
Fabricators who need a fast, traceable cost and a drawing pack for a small tank enquiry; engineers and estimators who need a first-principles check of a quote; and project teams that want a budget price with an honest list of what is not included.
| Item | Covered |
|---|---|
| Tank type | Shop-built, atmospheric (no internal pressure other than liquid head), full of liquid at design |
| Size | Capacity 0.5 to 100 m³; inside diameter 0.6 to 4.0 m (road transport limit); shell height 0.5 to 12 m |
| Layouts | Vertical on legs, skirt or slab; horizontal on saddles (Figure 1.2) |
| Two modes | Designed by this tool: the tool sizes the tank, runs the design checks and issues the calculation book. Designed by the client: you enter the client's thicknesses and details; the tool gives the fabrication estimate and drawings only, and lists any point to raise with the client |
| Services | Dairy (hygienic, 316L default), sulphuric acid 93 to 98 % (carbon steel), and general liquids; each starts from a template you can change |
| Materials | Carbon steel, stainless 304, stainless 316L |
| Design standard | API 650 (Annex J, shop-built tanks) or AS 1692 with AS/NZS 1170.2 wind (Australia) |
| Fittings | Any number of nozzles and manways, each on its own card: size, type, angle, height and projection; sanitary, flanged or coupling; a separate nozzle orientation drawing |
| Options | Insulation and cladding, agitator (top or side entry), cooling jacket (dimple or half-pipe), one-way sloped bottom, leg rings |
| Currency | AUD by default, any currency by exchange rate; prices exclude GST and tax |

| Quantity | Source |
|---|---|
| Plates, formed heads, legs | Computed from geometry and plate stock sizes (no catalogue exists for these); weight from density |
| Pipe, flanges, fittings, sanitary sets | Catalogue database weights and prices; weights are never computed from geometry |
| Plate prices | Database (per kg by material, converted to your currency); you can override rolling with a subcontract rate |
| Man-hours | Built activity by activity from weld lengths, plate counts, fit-up, test and inspection rules |
| Labour cost | Hours multiplied by your three all-in rates: shop, engineering and NDT |
| Allowable stresses, minimum thicknesses | Declared assumptions inside the engine, listed in the calculation report |
Where a figure is an assumption rather than data, the report says so. Prices are budget level, in 2026 dollars, and stay valid only until a vendor or workshop quote replaces them.
12345678910Figure 1.3 The tool page with a milk tank loaded. The numbers match the key below.
The tool is free to use on screen. You can enter any tank, watch the 3D model, read the cost and weights, and see the drawings.
| Free preview on screen | Purchased report | |
|---|---|---|
| Cost, price, man-hours, weights | Full | Full |
| Drawings | Low resolution, marked PREVIEW, NOT VALID | Clean A4 vector sheets |
| Report and calculations | Check summary in full; report and calculation sheet: first page only, the rest is blurred | Complete PDF |
| Excel and Word | Not available | Live-formula workbook and editable Word file |
| Ids and verification | Not issued; ids are registered and verifiable only after purchase | Report id, project id, revision code and check code |
To buy, press a download button, sign in with a six-digit code sent to your email, and pay by card. Files are produced on the server only after payment is confirmed, you receive a tax invoice, and you can download again for 12 months. One revision within 24 hours of purchase is free. Prices and offers are shown on the site at the time of purchase.
Email support@estineer.com with your report id. The check code lets us reproduce your exact result.
This chapter takes you from an empty page to a priced tank with drawings in five steps. The example is the 10 m³ milk tank that loads when you open the tool. Every field you skip keeps a sensible default, so a first result appears after step 2.

Type a project name. It prints on the report cover only.
Give the tank a tag, for example T-102. It names every drawing and file.
Pick a template: Milk / dairy, Sulphuric acid 93–98 %, General / water, or Custom. A template fills typical values for material, closures, supports, nozzles and finish. Every field stays editable afterwards.
Leave Design by the client unticked if this tool should size the tank and issue the calculations. Tick it when the client has already designed the tank and you only need the fabrication estimate and drawings (Chapter 3).
Choose the design standard and check the stored liquid and hygienic box.

Choose By capacity and type the volume in m³. The tool picks a diameter and height that suit road transport and a sensible height-to-diameter ratio.
Or choose By dimensions and type the inside diameter and shell height (or length, for horizontal tanks) in mm.
Pick vertical or horizontal. The result updates as soon as you leave a field.

Confirm the top and bottom closures, the supports and the material. A combination the tool does not design (for example a flat bottom on a skirt) gives a plain message instead of a result (Section 3.4).
Set the liquid density, design temperature, corrosion allowance and wind (0 for a tank installed indoors).
Leave Plate thickness on Minimum calculated unless the client has specified thicknesses.
Pick the finish and, if needed, the insulation thickness. Changing the material sets the finish for you (stainless: polish and passivate, CA 0; carbon steel: blast and paint); you can still change both.
Open the Nozzles tab to check the openings the template added. Each nozzle is a card: click it to change the mark, service, size, location, type, flange class, angle, position and projection, or press Add nozzle. Grey numbers are the engine's automatic values; type a number to fix your own.


Under Process options choose an agitator and a cooling jacket if the service needs them.
Under Workshop rates set the currency and its rate to the US dollar, your three all-in hourly rates (shop, engineering, NDT), contingency, markup, crew size and hours per week. These change cost and duration, never the design.
The result panel shows the title line, four result cards and the download buttons. Read the amber open items and checks first: they are the points an engineer must confirm. Then look through the tabs (Chapter 5).

Download PDF report gives the complete report: cover, estimate, calculations and all drawings in one file. Drawings only, Export Excel and Export Word give the other files. On the website, a download asks you to sign in with an emailed code and pay for the report; the files are then made on the server.
Fields are listed in screen order. Limits give the hard limit (outside it the tool stops and says why, in red) and, in brackets, the usual range (outside it the tool runs but asks you to confirm, in yellow). A dash means the field is a choice, not a number.
| Field | What it means and what it changes | Default | Limits |
|---|---|---|---|
| Project name | Printed on the report cover. No effect on the design or price. | empty | – |
| Tag | Equipment number. Names the drawings (for example ESTN-T-102-01) and the files. | T-102 | – |
| Template | Milk / dairy, Sulphuric acid 93–98 %, General / water, or Custom. Fills typical material, closures, supports, nozzles, density, temperature and finish. Custom keeps what you typed. | Milk / dairy | – |
| Design by the client | Ticked: you enter the client's thicknesses and sizes; the tool keeps them, prices the fabrication and draws the tank, and lists failed background checks as points to raise with the client. No calculation book is issued. Unticked: the tool sizes the tank and issues the calculations. | unticked | – |
| Design standard | API 650 (Annex J, shop-built tanks, selected methods) or AS 1692 with AS/NZS 1170.2 wind. Sets minimum thicknesses, joint efficiency, wind method and the code references in the report. | API 650 | – |
| Stored liquid | Name of the product, printed on drawings and reports. | by template | – |
| Hygienic design | Self-draining bottom, polished product surfaces, sanitary clamp fittings, continuous welds ground flush inside. Adds polishing and passivation work. | on for dairy | – |
| Field | What it means and what it changes | Default | Limits |
|---|---|---|---|
| By capacity / By dimensions | Capacity: the tool chooses the diameter and height. Dimensions: you give them. | By capacity | – |
| Capacity, m³ | Geometric volume to the top of the shell. | 10 | 0.5 to 100 |
| Orientation | Vertical or horizontal (Figure 1.2). | Vertical | – |
| Inside diameter, mm | Shown with By dimensions. Road transport limits it to 4 m. | 2000 | 600 to 4000 |
| Shell height / length, mm | Vertical: shell height. Horizontal: length between tangent lines. | by capacity | 500 to 12000; H/D 0.5 to 4, L/D 1 to 6 |
| Field | What it means and what it changes | Default | Limits |
|---|---|---|---|
| Top / roof | Torispherical, 2:1 ellipsoidal, cone, dome, flat or open top (Figure 3.1). An open top moves roof nozzles to the upper shell and drops the vent and manway. | by template | – |
| Cone roof angle, ° | Slope of a cone roof from horizontal. API 650 asks for 9.5 to 37°; outside it the check is NOT OK. | 10 | 5 to 45 |
| Bottom | Flat, flat sloped one way, torispherical, 2:1 ellipsoidal or cone (Figure 3.2). Formed and cone bottoms drain to a centre outlet. | by template | – |
| Bottom slope, ° | For the sloped flat bottom: the plate is tilted one way, low side at 90°, to a side outlet. | 2 | 1 to 10 |
| Cone bottom angle, ° | Slope of a cone bottom from horizontal. A steeper cone drains better and needs a thinner plate and a smaller junction ring. | 15 | 5 to 60 |


| Field | What it means and what it changes | Default | Limits |
|---|---|---|---|
| Supports | Legs, skirt or on slab (horizontal tanks: saddles). Changes the support design, the wind and overturning checks, and the anchors. Legs, rings, pads, skirt, base ring, chairs and bolts are sized on the final weight. Not designed (plain message instead of a result): a flat or sloped bottom on a skirt, and a formed or cone bottom on a slab. A flat bottom on legs needs a beam grid under the plate; a dished or cone bottom is the usual choice. | by template | – |
| Leg attachment | Pads plus two support rings (calculated by the tool) or plain pads (local shell stress to be checked by the engineer, WRC 537 or FEA). | Pads + 2 rings | – |
| Number of legs, Leg pipe size | Shown in Design by the client mode, vertical tanks on legs. Auto lets the tool choose from the load and slenderness. | auto | 3, 4, 6 or 8 legs; NPS 2 to 8 |
| Skirt thickness, mm | Shown in Design by the client mode on a skirt. | auto | 3 to 20 |
| Material | SS316L, SS304 or carbon steel (CS). Sets allowable stress, plate prices, welding process and finish options. | by template | – |
| Plate stock, W × L mm | Plate size the shell is cut from. Sets the number of courses, plates per course and the weld length. | 1500 × 6000 SS, 1800 × 6000 CS | – |
| Rolling and forming | In our shop, or Subcontractor. Subcontracted rolling is shown as a vendor item unless you type the roller's rate per kg. | In our shop | – |
| Plate thickness | Minimum calculated: the tool selects the next stock plate above every requirement. Custom: you type shell, bottom and roof thicknesses; a value below the minimum fails its check and the minimum is used instead (Design by the client keeps it). | Minimum calculated | – |
| Corrosion allowance, mm | Added to every pressure-part thickness and checked on nozzle and manway necks. | by template | 0 to 6 (up to 3) |
| Field | What it means and what it changes | Default | Limits |
|---|---|---|---|
| Liquid density, kg/m³ | Sets the hydrostatic load. Water (1000) is used if the product is lighter, so the hydrotest also governs. | by template | 500 to 2000 (700 to 1850) |
| Design temperature, °C | Reduces the allowable stress and modulus of stainless steel above ambient. | by template | −20 to 260 (0 to 95) |
| Wind, km/h (0 = indoor) | API 650 basic wind speed. With AS 1692: wind region, terrain category and return period replace it. | 0 dairy, else 160 | 0 to 250 |
| Finish | Polish, pickle and passivate (stainless) or blast and paint. Changing the material sets it (and CA 0 for stainless); a painted stainless tank or a CA above 1 mm on stainless gives a yellow warning. | by material | – |
| Insulation, mm; Insulation extent | Hygienic tanks: PU foam with stainless cladding; other tanks: mineral wool with aluminium cladding. Full tank or shell only. Adds weight, cost and man-hours. | 0 | 0 to 200 (25 to 100) |
| Field | What it means and what it changes | Default | Limits |
|---|---|---|---|
| Agitator | None, top entry (centre) or side entry. The tool adds the mounting nozzle and pad, checks the mount and lists the agitator itself as a vendor item. Vertical tanks only. | top for dairy | – |
| Agitator power, kW | Sets the nozzle size and the mounting check. | 0.75 | 0.18 to 15 (0.25 to 5.5) |
| Cooling jacket | None, dimple plate or half pipe. Adds jacket plate or pipe, welds, a separate jacket pressure test and its connections. Vertical tanks only. | None | – |
| Jacket height, % of shell | Share of the shell height covered by the jacket. The jacket stays clear of the leg pads, support rings and lifting lugs; if less is free, the tool warns and uses what fits, and stops below 300 mm. Shell nozzles in the jacket zone get cut-outs (warning). | 75 | 20 to 95 (40 to 90) |

Each opening is a card in the Nozzles tab. Marks starting with M are manways. Empty fields take the engine's automatic value, shown in grey.
| Field | What it means and what it changes | Default | Limits |
|---|---|---|---|
| Mark, Service | Tag and duty, for example N2 Outlet. The service picks the default type and flange. | by template | – |
| Size | NPS 1/2 to NPS 24. | by service | – |
| Location | Top / roof, shell high, shell, shell low, or bottom. | by service | – |
| Type, Flange class | By service (auto), slip-on, weld neck, clamp or coupling; Class 150 or 300. | auto | – |
| Angle, ° | Plan angle clockwise from north. Horizontal tanks: 0 = top, 90 = side, 180 = bottom, viewed from the left end. | auto, clear of seams and lugs | 0 to 360 |
| Position, mm | Shell: elevation above the shell bottom. Roof: distance from the centre. Horizontal: distance from the left tangent line. | auto | inside the shell or roof |
| Projection, mm | From the shell or head outside to the flange face. | by size | 50 to 500 |
| Field | What it means and what it changes | Default | Limits |
|---|---|---|---|
| Currency, Rate per 1 USD | Currency of every cost and price. The database is in US dollars; the rate converts it. | AUD, 1.4706 | > 0 |
| Shop labour, Engineering, NDT (per hour, all-in) | Your three all-in labour rates. Man-hours are multiplied by the rate of their group. | 110 / 150 / 160 AUD | equivalent 10 to 300 USD/h |
| Contingency, % | Added to the direct cost for unknowns. | 10 | 0 to 50 (5 to 25) |
| Markup, % | Profit on cost: price = cost × (1 + contingency) × (1 + markup), rounded up to the next 50. | 15 | 0 to 50 (5 to 30) |
| Crew, Hours / week | Workshop crew and working week. Change the duration only. | 4, 38 | 1 to 20; 20 to 84 (36 to 60) |
In the Cost tab every material cost and every activity's man-hours can be typed over. Press Enter to apply. Edited values are marked in the report, and a value more than 50 % away from the tool's figure raises a yellow warning.
The calculation report follows the order below. Each row shows the formula, the numbers put into it and the result, so an engineer can check it by hand. The methods are the selected methods of the chosen standard for shop-built atmospheric tanks; where the tank is outside a standard's scope (for example a suspended bottom on legs), the report says so and states the method used.
Tag, service, standard, orientation, material, inside diameter, shell height, closures, geometric capacity, design liquid level, specific gravity G = max(1.0, density / 1000), design pressure (atmospheric, full of liquid), design temperature, corrosion allowance CA, joint efficiency E = 0.85 (spot radiography) and the allowable design stress Sd.
| Quantity | Formula |
|---|---|
| Design thickness td | 4.9 D (H - h0) G / (Sd E) + CA |
| Test thickness tt | stainless: 4.9 D (H + x - h0) / (St E), AS 1692 x = 1 m; carbon steel: AS 1692 with Sd, API 650 hydrotest check only |
| Reduction h0 | 0.3 m only where a flat (or one-way sloped) bottom restrains the shell foot; 0 for formed and cone bottoms and for horizontal tanks |
| Minimum nominal | standard table for the diameter (+ CA where the standard requires) |
| Check (corroded) | 4.9 D (H - h0) G / (tn - CA) ≤ Sd E |
| Quantity | Formula |
|---|---|
| Pressure at the lowest point | P = max(density, 1000) × 9.81 × H_total; AS 1692: the larger of the product to the design level and water to the top plus 1 m (test head of clause 2.8.2) |
| Formed bottom or head | th = P D M / (2 Sd E) + CA, then × 1.1 forming thinning; M = 1.54 torispherical, 1.0 ellipsoidal |
| Formed head minimum | standard minimum + CA, and t - CA ≥ 0.002 L (L = D torispherical, 0.9 D ellipsoidal); horizontal heads at most one plate step thinner than the shell |
| Cone bottom | th = P D / (2 cos b Sd E) + CA, not less than the minimum + CA |
| Cone/shell junction | Q = P R / 2 tan b ; A_req = Q R / (0.6 Sd) ; A_av = 0.78 √(R t) t for cone and shell, corroded; ring added for the shortfall |
| Flat bottom | CS: 6 mm + CA ; stainless: corroded thickness ≥ 5 mm |
| Top head or roof | no hydrostatic load: minimum + CA; cone, flat and dome roofs checked for self-weight and roof load |
Automatic selection uses the same total head as the printed check, so a selected bottom always passes its own calculation. A thickness you type below the requirement is not used: the tool keeps the required thickness and marks the check NOT OK. Only in Design by the client mode is the typed thickness kept, as a point to raise with the client.
| Quantity | Formula |
|---|---|
| Shell openings > NPS 2 | A_req = d × t_req (t_req at the opening's own liquid head) ; A_av = d (tn - CA - t_req) + 2 × min(4 t_neck, 8 tn) (t_neck - CA) + pad |
| NPS 2 and smaller | exempt from reinforcement (API 650 5.7.2.1); neck wall still checked |
| Openings in a formed or cone bottom | area replacement at the pressure of the lowest point, plus neck hoop stress P (OD - t) / (2 (t - CA)) ≤ Sd |
| Openings in a top head or roof | above the liquid: no pressure; local load check on the parent plate |
| Horizontal tanks | every opening is below the liquid (design level = full diameter); head at the opening's lowest edge = R (1 - cos a) + OD/2 |sin a| |
| Neck walls | after 12.5 % mill tolerance and CA ≥ 1.5 mm; manway necks keep their table minimum after CA |
| Shell manway cover and ring | standard table entered with the equivalent head = liquid height × max(G, 1); above 8 m the table thickness is scaled by √(head / 8) and marked open for the engineer |
Empty, operating (normal fill), full of product to the design level and hydrotest (full of water) weights, each from the material take-off. Centres of gravity are estimated from part elevations and reported for information; the weights size the supports and the lifting lugs.
| Quantity | Formula |
|---|---|
| API 650 | shell 0.86 kPa and roof uplift 1.44 kPa at 190 km/h, scaled by (V / 190)² |
| AS/NZS 1170.2 | Vdes = VR (× 1.05 region C, 1.10 region D, for R of 50 years or more; regional speed confirmed where the map shows subregions) Md Mz,cat, not less than 30 m/s ; q = 0.6 Vdes² ; shell Cfig 0.63 ; roof Cp,e mean 0.65 |
| Force | Fw = Pws × projected area (for a skirt, down to the base ring) |
| Moment at the support base | Mw = Fw × arm (+ roof uplift moment, vertical tanks) |
| Quantity | Formula |
|---|---|
| Legs, axial | KL = 2 × free length ; λ = KL / (r π) √(fy / E) ; P_all = A fy / (1.67 (1 + λ²)) |
| Legs, wind | P_ot = 4 Mw / (n Dc) ; P / P_all + fb / (0.66 fy) ≤ 1 ; uplift when empty > 0 needs anchored base plates |
| Leg pads | pad length chosen from 300 to 1000 mm so that the leg-to-pad welds and the shell shear pass; the legs, rings and drawings use the same length |
| Leg rings and welds | rings at the top and bottom of the pad; radial couple F = Pd (e + t/2) / hr; ring bending, leg-to-ring welds, ring-to-shell welds (stitch 1/3, 1/2 or continuous), shell bearing; anchor bolts M16 to M30 from the uplift |
| Skirt | W / A + Mw / Z ≤ allowable with the section reduced at the access opening and yield at temperature; skirt-to-head weld; base ring and anchor bolts increased until bearing, ring bending and bolt stress pass |
| Flat bottom on legs | plate between beams; beams for bending, deflection L/360, wall ≥ 3 mm, compact flange and web, and web shear at the end clips |
| Final weight | supports are sized on the finished empty weight; if jacket, insulation or welds make the tank heavier than the sizing weight, the whole model is run again |
| Saddles (horizontal) | Saddle stress analysis: longitudinal bending, shear, horn stress, wear plate edge, ring compression at the saddle and, when A ≤ R/2, head shear and head stress; wear plate b + 1.56 √(R t) wide; the shell is thickened until all pass, otherwise the tool stops |
| Quantity | Formula |
|---|---|
| Lug load | 2 × empty weight shared by the lugs, sling at 60°, safety factor 4 on ultimate |
| Lug plate | net tension, tear-out and pin bearing |
| Lug-to-pad welds | full moment from both components: vertical tank M = Fv b/2 + Fh |h/2 - a|; horizontal tank M = Fh (b - a); combined stress ≤ 0.6 Fe / 4; the lug size is raised until it passes |
| Pad-to-shell weld and shell | weld group with the moment including the pad thickness; shell shear around the pad; local shell bending left open for the engineer |
| Overturning, tank on slab | resisting weight = corroded shell and roof only (no bottom, no liquid); anchor chairs and bolts chosen from 4 × M24 up to 8 × M30 |
| Quantity | Formula |
|---|---|
| Agitator mount | nozzle and pad sized from the power; weld and wall checked on the corroded wall; local loads (WRC 107 / 297 or FEA with the vendor's loads) open for the engineer |
| Cooling jacket | plate or half pipe sized for 3 bar g, panel stress on the corroded shell; separate jacket pressure test. The jacket is pressure equipment: AS 1210 (dimple plate by clause 3.16.6, half pipe by clause 3.23), hazard level and registration by the engineer |
| Hydrotest | full of water to the top of the shell (AS 1692: plus 1 m); shell stress 4.9 D (H - h0) / tn ≤ St E ; 4 h hold, no leaks |
Every weld in the weld register carries its own inspection requirement, and the priced activities count from the register:
| Quantity | Formula |
|---|---|
| Material | Σ take-off items: plates from geometry and stock size, catalogue items from the database |
| Man-hours | Σ activities: quantity × crew × hours per unit × modifiers (material, position, thickness) × 1.2 allowance |
| Labour | engineering MH × engineering rate + shop MH × shop rate + NDT MH × NDT rate |
| Direct cost | material + labour, rounded up to the next 50 |
| Indicative price | direct cost × (1 + contingency) × (1 + markup), rounded up to the next 50 |
| Duration | engineering and approval, procurement, shop man-hours / (crew × hours per week), testing, dispatch |
The result panel has four result cards and seven tabs. Tabs can be put in your own order with Arrange tabs.
| Direct cost | Material plus labour at your rates, rounded up to the next 50. Ex-works, excluding vendor items listed in red. |
| Indicative price | Direct cost with contingency and markup, before tax. |
| Man-hours | Total, split into engineering, shop and test (NDT, hydrotest, dimensional). |
| Duration | Weeks from order, for your crew and working week. |

The build-up groups material and labour lines. Below it, every material item and every activity can be edited (Section 3.9). Site installation is shown separately and is not in the price.


The nozzle cards (Section 3.7) with a live plan and front elevation. Click a card or a balloon to highlight the nozzle in the 3D model. The same layout prints as the Nozzle orientation drawing.
The design status (calculated checks passed and open items), the notes from the engine, and the full calculation sheet in the order of Chapter 4.

| Sheet | Content |
|---|---|
| 01 GA views | Plan, elevation, isometric, nozzle schedule, design data and notes |
| 01-2 GA schedules | Nozzle schedule, design data and notes of the GA at a readable size |
| NO Nozzle orientation | Orientation plan (or end view), developed shell with seams, pads and openings, nozzle table |
| S01 Shell development | Plates, seams and openings laid flat with dimensions |
| S02 Cutting and material list | Plate cutting plan and the full material list |
| S03 to S05 Weld details | W1 to W6: shell seams, bottom to shell, nozzle neck, flange, supports, lug |
| S06 Welding notes | Processes, consumables, preparation, inspection and finish notes |
| S07 Weld schedule | Every registered weld: joint, type, size, length, process and NDT |
| S08 Nozzle detail schedule | Neck, flange or ferrule, pad, projection and weld for each opening |
Sheets are A4, numbered with the tag (for example ESTN-T-102-S07) and marked FOR REVIEW.

The PDF report holds the cover (with the 3D picture, ids and the full responsibility statement), the estimate (basis, cost build-up, exclusions, schedule, inputs to confirm), the calculation report and all drawing sheets, with bookmarks and a linked contents list.
| File | What it is |
|---|---|
| PDF report | The reference document: estimate, calculations and drawings. Searchable text, bookmarks. |
| Drawings (PDF) | The A4 drawing set on its own. |
| Excel | Live-formula workbook: inputs as named cells, material and activity tables, cost build-up. Change a rate and the price follows. A working copy only. |
| Word | Editable report text for your own offer or notes. A working copy only. |
| Project id | EP-XXXX-XXXX, one per tank tag. |
| Report id and revision | ER-XXXX-XXXX Rev A, one per set of inputs; each issued revision also gets a revision code RV-XXXX-XXXX. |
| Check code | XXXX-XXXX, made from the inputs, the engine version and the database. The same inputs always give the same code. |
The ids are printed on the cover, the page footers, under every drawing frame, and in the Excel and Word files. Anyone can enter a report id at estineer.com/verify to see whether it is genuine, its date and the tank; prices and the buyer are never shown.
The screen shows every number for free. Drawings on screen are low-resolution and marked PREVIEW, NOT VALID; the Report tab shows the cover only, and the Calculations tab shows the design status, check summary and notes with the full calculation sheet blurred after its first page. After purchase the files are clean and complete, and can be downloaded again for 12 months.
The 10 m³ milk tank T-102 is the tank that loads when the tool opens. Every number below comes from the engine with the inputs in Section 6.1, engine version 1.64; you can reproduce them on screen.
| Field | Value |
|---|---|
| Template, liquid | Milk / dairy, milk, hygienic |
| Capacity | 10 m³, vertical |
| Closures, supports | 2:1 ellipsoidal top, 15° cone bottom, 4 legs with pads and 2 support rings |
| Material, finish | SS316L, polish, pickle and passivate |
| Density, temperature, CA, wind | 1030 kg/m³, 95 °C, 0 mm, indoor |
| Agitator, jacket | top entry 0.75 kW, none |
| Nozzles | N1 inlet, N2 outlet, N3 CIP spray ball, N4 vent, N5 level, N6 temperature, N7 sample, M1 manway NPS 18 |
| Rates | shop 110, engineering 150, NDT 160 AUD/h; contingency 10 %, markup 15 %; crew 4, 38 h/week |
| Item | Value |
|---|---|
| Inside diameter × shell height | 2,050 × 2,950 mm |
| Geometric capacity | 10.04 m³ |
| Shell | 5 mm, 2 courses of 2 plates from 1500 × 6000 stock |
| Design liquid level from the apex | 3,225 mm |
| Cone bottom / top head | 5 mm / 5 mm |
| Legs | 4 pipe legs NPS 2-1/2, 1,175 mm long |
The calculation report gives the full working; the summary is below.
| Check | Value | Limit | Result |
|---|---|---|---|
| Shell hoop stress ratio (corroded) | 0.06 | 1.00 | OK |
| Cone bottom thickness | 5.00 mm | 1.17 mm | OK |
| Cone/shell junction area | 819.72 mm2 | 819.72 mm2 | OK |
| N2 bottom opening reinforcement | 335.62 mm2 | 4.15 mm2 | OK |
| M1 manway in top head (local load) | 0.28 MPa | 58.83 MPa | OK |
| Leg axial (full of product to design level) | 0.68 | 1.00 | OK |
| Leg axial + bending (full of product + wind) | 0.68 | 1.00 | OK |
| Leg-to-pad fillet welds | 17.55 MPa | 144.00 MPa | OK |
| Shell shear at leg pad | 9.55 MPa | 58.83 MPa | OK |
| Leg support ring bending | 83.62 MPa | 97.08 MPa | OK |
| Leg-to-ring welds | 7.92 MPa | 144.00 MPa | OK |
| Ring-to-shell stitch welds | 32.90 MPa | 144.00 MPa | OK |
| Shell bearing at the lower leg ring | 11.20 MPa | 132.38 MPa | OK |
| Leg uplift, empty + wind (no anchors needed) | -3.29 kN | 0.00 kN | OK |
| Lifting lug 120 x 10 plate and welds | OK | SF 4 on ultimate | OK |
| Lug pad weld and shell shear | 0.13 | 1.00 | OK |
| Local shell bending at lifting lugs | not calculated | engineer | open |
| Agitator mount | OK | pad on wall | OK |
| Hydrotest shell stress | 5.93 MPa | 131.75 MPa | OK |
Example by hand, cone bottom: P = 1030 × 9.81 × 3.225 = 32.6 kPa; th = 0.0326 × 2,050 / (2 × cos 75° × 130 × 0.85) = 1.17 mm, so the 5 mm minimum thickness of the standard governs and the adopted plate is 5 mm.
| Line | MH | AUD |
|---|---|---|
| Plates, heads and structural | 14,758 | |
| Nozzles, flanges and manway | 3,573 | |
| Supports, lugs and access | 1,723 | |
| Agitator mounting and cooling jacket | 237 | |
| Consumables, surface treatment and finishing | 724 | |
| Engineering, calculations and drawings | 44.4 | 6,660 |
| Shop fabrication | 222.5 | 24,470 |
| NDT (visual, radiography, penetrant) | 38.7 | 6,188 |
| Hydrotest and dimensional inspection | 14.4 | 1,585 |
| Material + labour | 319.9 | 59,917 |
| Direct cost (rounded up to 50) | 59,950 | |
| Contingency 10 %, markup 15 % | × 1.10 × 1.15 | |
| Indicative price (rounded up to 50) | 75,850 |
Check: 59,950 × 1.10 × 1.15 = 75,837, rounded up to 75,850 AUD.
| Item | Value |
|---|---|
| Empty / operating / full / hydrotest | 1,341 / 11,164 / 11,681 / 11,380 kg |
| Weld length | 66 m |
| Duration | 7 weeks from order: engineering 1.5, procurement 3 (starts in week 1, overlapping engineering), fabrication about 1.5, testing 1, dispatch 0.5 |
Small tanks are usually governed by the minimum thickness of the standard, the next stock plate, or a support or nozzle check, not by the hoop stress. The calculation report shows which.
A value is outside its hard limit (Chapter 3), or the combination is one the tool does not design (Section 7.1). The message says what to change.
With Minimum calculated thickness the tool fixes most checks itself. A NOT OK usually follows a value you typed (a custom thickness, a nozzle position) or a client design. Change the input, or raise the point with the client.
It is a vendor item. The tool prices its nozzle, pad and installation, and lists the agitator in the red box so you add the vendor's quotation.
Yes, in the Cost tab. Your edits are marked in the report, and large changes raise a warning.
Yes, while the engine version and database stay the same. The check code changes when either changes.
The engineer who checks and approves it. The tool gives engineering data and a cost model, not engineering advice and not a quotation.
| Annex J | API 650 annex for shop-built tanks |
| CA | Corrosion allowance, added to thicknesses |
| Course | One ring of shell plates |
| Direct cost | Material plus labour, before contingency and markup |
| E | Joint efficiency, 0.85 for spot radiography |
| Ex-works | Price at the fabricator's workshop, before transport |
| G | Design specific gravity, at least 1.0 |
| GA | General arrangement drawing |
| Hydrotest | Test full of water before dispatch |
| Markup | Profit added on cost |
| MH | Man-hours |
| MTO | Material take-off: every item with weight and cost |
| NDT | Non-destructive testing: VT visual, RT radiography, PT penetrant, MT magnetic particle |
| NPS | Nominal pipe size |
| Open item | A point the engineer must confirm |
| Pad | Reinforcing plate around an opening or under a leg or lug |
| Sd, St | Allowable design and hydrotest stress |
| SPECIFIED | A requirement met by the specification, with no number to check |
| Support base | The plane the overturning moment is taken about: leg feet, or under the skirt base ring |
| Tag | Equipment number, for example T-102 |
| Vendor item | Bought-in item priced from a quotation, not by the tool |
Email support@estineer.com with your report id and check code.